76 10/3239M-Re-Development of depot for residential dwellings (maximum 50 dwellings), Cold Storage, Knutsford Road, Chelford for Mr Greg Williams, Eddie Stobart Group Ltd
PDF 166 KB
To consider the above application.
Additional documents:
Minutes:
Consideration was given to the above
application.
(Parish Councillor Mrs Gildon, Chairman of Chelford Parish Council and Mrs C Payne, agent for
the applicant attended the meeting and spoke in respect of the
application).
RESOLVED
That the application be approved subject
to the following Heads of
Terms:-
- The Employment
element as proposed under application 10/3267M shall be
substantially complete within 3 years of the commencement of the
residential scheme unless another scheme is approved in writing
with the Local Planning Authority
- 30%
affordable housing split between 50% for social rent and 50% for
intermediate ownership but with flexibility to vary the
proportions of tenure in line with guidance from the Homes &
Communities Agency and the Council`s Strategic Housing Manager
current when layout details are submitted for reserved
approval.
- Provision of a Puffin
Crossing on Knutsford Road
(A537)
- Provision of public
footpath, linking the existing bridle path to Knutsford Road
- Education
contribution of £68,750 towards extending Chelford CE Primary School, to accommodate
additional school children generated by the development
- Commuted sum of
£187,000 in lieu of Public Open Space /off site play &
amenity facilities/recreation and outdoor sport
- Financial
contribution towards community facilities £30,000
And subject to the following
conditions:-
- A06OP
- Commencement of
development
- A03OP
- Time limit for submission of reserved
matters (within 3 years)
- A01OP
- Submission of reserved matters
(within 3 years)
- A02OP_1 - Implementation of reserved matters
- A09OP
- Compliance with parameter
plans
- A10OP_1 - Details to be submitted -layout
- A12OP
- Full details approved as part of
outline consent - Access
- A08OP
- Ground levels to be
submitted
- A01LS
- Landscape Masterplan - submission of
details
- A04LS
- Landscaping
(implementation)
- A01GR
- Removal of permitted development
rights
- A02HA
- Construction of access
- A04HA
- Vehicular visibility at access to be
approved
- A32HA
- Submission of construction method
statement
- A19MC
- Refuse storage facilities to be
approved
- At least 10% of the energy supply of the development shall be
secured from decentralised and renewable or low-carbon energy
sources
- Phasing of landscaping works - along railway line
first
- Submission of a landscape management scheme to be submitted with
the Reserved Matters application
- The landscaping scheme shall incorporate details of boundary
treatment
- Protection of breeding birds
- Provision of bird boxes
- All arboricultural works shall be carried out in accordance with
Cheshire Woodlands Arboricultural Statement
- Details of lighting to be approved
- Development in strict accordance with the updated ecological
survey
- Submission of further acoustic assessment showing acoustic
mitigation as part of Reserved Matters application
- Submission of acoustic report including a revised assessment of
noise levels at the North East corner
- Submission of specifications of acoustic glazing ventilation
systems
- Hours of construction/noise generative works
- Submission of revised air quality assessment
- Submission of a drainage scheme including details in respect of
surface water run-off
- Submission of a scheme to manage the risk of flooding to be
submitted
- Submission of a Character Assessment justifying scale, layout
and materials as part of the Reserved Matters
application
- To control hours of working and pile ...