To consider the above application.
Minutes:
Consideration was given to the above planning application.
The following attended the meeting and spoke in relation to the application:
Ward Councillor: Councillor Ashley Farrall
Agent / Applicant: Megan Sadler
RESOLVED:
For the reasons set out in the report, and the update report, the application be APPROVED, as RECOMMENDED, subject to a S106 Agreement to secure:
S106 |
Amount |
Trigger |
NHS |
£52,762 towards improved health infrastructure facilities at Waters Green Medical Centre, Macclesfield |
Pre-commencement |
and the following conditions / informatives:
1. Commencement of development (3 years)
2. Development in accord with approved and amended plans
3. Materials to be submitted including details of surfacing
4. Details of window reveals to be submitted, approved and implemented with minimum reveal of 100mm
5. Details of fenestration to be submitted including colour (to be dark and not UPVC)
6. Details of recessed brickwork, including brick “soldier courses” and the external cladding to be submitted, approved and implemented
7. Details of scheme of public realm works to Park Green frontage to be submitted
8. Revised landscaping - submission of details
9. Landscaping (implementation)
10. Submission, approval and implementation of Arboriculture Arboricultural Impact Assessment and Method Statement
11. Submission, approval and implementation of a revised Tree Protection Scheme
12. Accordance with submitted Ecological Assessment
13. Nesting birds survey to be submitted
14. Submission, approval and implementation of a habitat creation method statement and a 30-year habitat management plan (Biodiversity Net Gain – Habitat Management Plan)
15. Submission, approval and implementation of an Ecological Enhancement Plan
16. Details of a sustainable surface water drainage scheme and a foul water drainage scheme to be submitted, approved and implemented
17. Accordance with submitted noise mitigation measures
18. Method statement for piling and floor floating to be submitted
19. Dust Management Plan for minimising dust emissions during demolition / construction to be submitted, approved and implemented
20. Accordance with submitted Electric Vehicle Charging Infrastructure and provided prior to first occupation
21. Any gas fired boilers to be low emission
22. Accordance with submitted Travel Plan
23. Phase I / II ground investigation and risk assessment to be submitted, approved and implemented
24. Verification report in accordance with remediation to be submitted and approved
25. Imported soil to be tested for contamination
26. Unforeseen contamination to be reported to LPA
27. 10% of energy to be secured from decentralised and renewable or low carbon sources
28. Programme of archaeological work in accordance with a written scheme of investigation to be submitted, approved and implemented
29. Parking provided in accordance with submitted details prior to first occupation
30. Construction Management Plan to be submitted, approved and implemented
Informatives:
1. NPPF
2. Biodiversity Gain Informative
3. Environmental Health Informatives
In the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions / informatives / planning obligations or reasons for approval/refusal) prior to the decision being issued, the Head of Planning has delegated authority to do so in consultation with the Chairman of the Strategic Planning Board, provided that the changes do not exceed the substantive nature of the Committee’s decision.
Supporting documents: