Agenda item

09/0819N - Land adjacent Pinnacle Farm, Coole Lane, Newhall, Nantwich: Change of Use from Agriculture to Fish-Rearing and Angling Centre and Formation of Ponds and Lakes, Erection of Buildings (including Temporary Dwelling) and Provision of Access and Parking for The Reilly and Seipp Partnership

To consider the above application.

 

Minutes:

Note:  Councillor Margaret Hollins (the Ward councillor), Mr Gary Waudby (objector) and Mr Brian Reilly (applicant) attended the meeting and addressed the Committee on this matter.

 

The Committee considered a report regarding the above planning application, and additional representations from local residents which were summarised by the Southern Area Manager – Development Management.

 

RESOLVED –

 

That the application be APPROVED subject to the following conditions:

 

1.         Standard

2.         Materials of the temporary dwelling and office to be submitted and approved in writing

3.         Materials of the hatchery building to be submitted and approved in writing.

4.         Materials of the polytunnels to be submitted and approved in writing.

5.         Materials of the toilet block to be submitted and approved in writing

6.         Surfacing materials to be submitted and approved in writing

7.         Access to be a width of 5.5m for the first 15m from Coole Lane with 10m radius

8.         Visibility splays of 2.4m x 120m to be provided and retained prior to the temporary dwelling is first being occupied

9.         Prior to the commencement of development a scheme of passing places along the access shall be submitted and approved. The approved details shall be implemented in accordance with a time table to be submitted and approved

10.       Setting back of gates 10.5m from Coole Lane and gates to open inwards only

11.       Width of access to be 3m wide apart from first 15m which shall be constructed in accordance with Condition 4

12.       Landscaping scheme to include all new woodland planting and wildflower areas outside the application site and reed beds, watercourse, settlement tanks, ponds and other planting

13.       Landscape implementation to be carried out in accordance with a timetable to be submitted and agreed

14.       Design of overflow channel screening to be submitted and approved in writing

15.       Details of any lighting to be submitted and approved in writing

16.       Any ancillary ancillary mounted equipment in connection with the temporary dwelling, fish rearing pools and hatchery building shall be acoustically attenuated in accordance with a scheme to be submitted and approved

17.       The location of mobile mechanical plant shall not be audible at the façade of the nearest noise sensitive premises

18.       Temporary dwelling and business facility (3 years only)

19.       Occupation of dwelling restricted to the fishing and angling centre use of the site

20.       Removal of PD for extensions/alterations for temporary dwelling

21.       Phasing plan for the development to be submitted and approved in writing

22.       Final site levels to be submitted and agreed in writing

23.       Biodiversity management plan to be submitted and approved win writing

24.       Drainage details to be submitted and approved in writing

25.       Storage and disposal of waste details to be submitted and approved in writing

26.       A scheme of bird nesting boxes and bat boxes to be submitted and approved and provided

27.       The development to be subject to a Green travel plan which shall be submitted and approved in writing

28.       Details of covered cycle parking to be submitted and approved and to be provided prior to lakes becoming open to fishing

29.       Development to be carried out in accordance with the approved plans

 

                                                               

 

 

Supporting documents: