To consider the above planning application.
Minutes:
Note: Councillor D Hough (Ward Councillor) attended the meeting and addressed the Committee on this matter.
The Committee considered a report regarding the above planning application.
RESOLVED
(a) That, for the reasons set out in the report, the application be APPROVED subject to the completion of a deed of variation to the S106 Agreement to application 13/4121C and the following conditions:
1. Standard Time – 3 years from 18th June 2015
2. Approved Plans
3. Prior to the commencement of development, a plan showing the extent of the phases of development (comprising the internal road infrastructure works referred to in Condition 34 –Phase 1 - and the remainder of the development – Phase 2) shall be submitted to the Local Planning Authority for approval in writing. The development shall proceed in accordance with the approved details.
4. Prior to the commencement of development details of existing and proposed land levels to be submitted to the LPA for approval in writing
5. The development hereby permitted shall not be commenced until such time as; a scheme to limit the surface water runoff generated by the proposed development, has been submitted to and approved in writing by the local planning authority.
6. The development hereby permitted shall not be commenced until such time as; a scheme to manage the risk of flooding from overland flow of surface water, has been submitted to and approved in writing by the local planning authority
7. With the exception of the internal road infrastructure the development hereby permitted shall not be commenced until such time as a scheme to install underground tanks associated with the petrol filling station has been submitted to, and approved in writing by, the local planning authority. The scheme shall include the full structural details of the installation, including details of: excavation, the tanks, tank surround, associated pipework and monitoring system. The scheme shall be fully implemented and subsequently maintained, in accordance with the scheme, or any changes as may subsequently be agreed, in writing, by the local planning authority.
8. The development hereby permitted shall not be commenced until such time as a scheme to dispose of surface water has been submitted to, and approved in writing by, the local planning authority. The scheme shall be implemented as approved.
9. If, during development, contamination not previously identified is found to be present at the site then no further development (unless otherwise agreed in writing with the local planning authority) shall be carried out until the developer has submitted a remediation strategy to the local planning authority detailing how this unsuspected contamination shall be dealt with and obtained written approval from the local planning authority. The remediation strategy shall be implemented as approved.
10. Contaminated Land
11. Construction hours, and associated construction deliveries to the site, shall be restricted to 08.00 to 18.00hrs Monday to Friday and 09.00 to 14.00hrs on Saturdays. There shall be no working on Sundays or Bank Holidays.
12. All piling operations shall be restricted to: Monday – Friday 09:00 – 17:30 hrs, Saturday 09:00 – 13:00 hrs, Sunday and Public Holidays Nil
13. Construction Management Plan
14. External Lighting Details
15. Hours of deliveries to the store and biomass boiler between the hours of 5am and 11pm (seven days a week) and that unrestricted (24 hour) deliveries to the petrol filling station
16. Details of Fixed Plant and Equipment
17. Scheme of security barriers for the proposed car park
18. A written schedule of maintenance for the Biomass Boiler which shall include removal of ash, inspection and maintenance of particulate arrestment equipment, boiler servicing and stack cleaning.
19. The biomass boiler shall only be operated using clean wood pellets that comply with a recognised fuel quality standard. A statement shall be submitted to the local authority specifying the quality of the wood pellets used in the biomass boiler and the fuel specification in accordance with CEN/TS 14961 or a similar recognised standard.
20. There shall be no changes to the fuel type for the Biomass Boiler, specification or operation of the biomass boiler unless agreed with the LPA
21. The Biomass stack shall comply with the parameter values specified in Table 5-1 of the submitted air quality assessment, report number 410.04063.00001-dated August 2013 with the exception of the stack height which shall not be less than 8.755 metres. Any deviations shall be submitted to and be approved in writing by the Local Planning Authority.
22. Prior submission and approval of materials
23. Prior to undertaking any works between 1st March and 31st August in any year, a detailed survey is required to check for nesting birds. Where nests are found in any building, hedgerow, tree or scrub to be removed (or converted or demolished in the case of buildings), a 4m exclusion zone to be left around the nest until breeding is complete. Completion of nesting should be confirmed by a suitably qualified person and a report submitted to the Council.
24. Nesting Bird Mitigation Measures
25. Mitigation recommendation of the 2014 Badger report to be secured
26. Boundary Treatment Details including details of all retaining structures
27. Tree protection measures
28. Arboricultural Method Statement
29. Implementation of the submitted landscape proposals
30. Cycle Parking Details
31. The net sales area shall be limited to 2,322sq.m
32. 1,975sq.m (85%) of the sales area will be for the display of convenience goods with the remaining 348sq.m for comparison goods.
33. Prior to first development the developer will provide a detailed suite of design and construction plans for the internal road infrastructure to the satisfaction of the LPA.
34. Prior to first use all access roads and car parking will be constructed and formally marked out.
35. Prior to the store first being brought into use the developer shall fully construct the following off-site highway works:
- The roundabout
access in accordance with plan reference A-PL-103 Rev J
- The new bus stops on the A5011 in accordance with plan reference
A-PL-103 Rev J
- The junction improvement works at the junction of the
A5011/A50/B5077 in accordance with Plan reference VN20017/104.
36. Prior to the commencement of development a plan to show the provision of a footway and cycleway from the site access with Linley Lane to the signal junction at the A5011/A50/B5077 cross-roads shall be submitted to the Local Planning Authority for approval in writing. The approved scheme shall be constructed in accordance with the approved details before the store or petrol station is first brought into use.
37. Travel Plan
38. Details of the opening of the culvert to be submitted to the LPA for approval in writing.
39. Prior to the commencement of phase 2 elevational details of all minor structures including trolley bays, sprinkler tanks, the biomass boiler and electrical services structures shall be submitted to the LPA for approval in writing.
(b) That, in order to give proper effect to the Committee’s intentions and without changing the substance of the decision, authority be delegated to Head of Planning (Regulation) in consultation with the Chairman (or in her absence, the Vice Chairman) of the Southern Planning Committee, to correct any technical slip or omission in the wording of the resolution, between approval of the minutes and issue of the decision notice.