Agenda item

15/0699C 19, Lawton Road, Alsager ST7 2AA: Variation of condition 9 (hours) attached to planning permission 10/0741C. Demolition of existing Co-operative Foodstore, Construction of new Co-operative foodstore, associated service area and retail units, Reconfiguration and refurbishment of existing town centre car park and public open space for ASDA Stores Ltd

To consider the above planning application.

Minutes:

Note: Ms E Philcox attended the meeting and addressed the Committee on behalf of the applicant.

 

Note: Ms J Taylor-Smith (applicant) had registered her intention to address the Committee but did not speak.

 

The Committee considered a report regarding the above planning application.

 

RESOLVED

 

(a) That, for the reasons set out in the report, the application be APPROVED subject to the following conditions:

 

1.            Within 3 months – submission of a Delivery Management Plan

2.            Development in accordance with approved amended plans received 29th April 2010 (10/0741C)

3.            Materials - as per discharge (27/10/2011)

4.            Restriction of retail floor space within the supermarket to 1318m² net retail floor space.

5.            Restriction on hours of opening for supermarket (as recently approved)

6.            Restriction on hours of opening of restaurant

7.            Restriction on hours of delivery for all units (as revised)

8.            Noise mitigation for delivery areas – as per discharge (27/10/2011)

9.            Noise mitigation for plant and equipment – as per discharge (07/03/2012)

10.         Refrigeration and/or air conditioning plant and equipment - Submission of details within 6 months

11.         Extraction equipment re cooking equipment – Submission of details within 6 months

12.         Bus stop upgrade details - Submission of details within 6 months

13.         New junction plans – as per discharge (07/03/2012)

14.         Final layout of the car parking area - as per discharge (27/10/2011)

15.         Signal junction installations - as per discharge (07/03/2012)

16.         TRANSYT Design - as per discharge (07/03/2012)

17.         Electric car charger points - as per discharge (27/10/2011)

18.         CCTV details - Submission of details within 6 months

19.         Public realm treatment strategy – as per discharge (07/03/2012)

20.         Footpath enhancement - as per discharge (07/03/2012)

21.         Surface water discharge rates - as per discharge (27/10/2011)

22.         Surface water regulation system timescales - Submission of details within 6 months

23.         Site to be drained on a separate system with only foul drainage connected into the foul sewer - as per discharge (27/10/2011)

24.         Standard landscaping - as per discharge (27/10/2011)

25.         Tree Protection - as per discharge (27/10/2011)

26.         Standard landscaping replacement planting within remaining period.

27.         Ecological enhancements (bat and bird boxes and tree planting to be native species) - Submission of details within 6 months

28.         Roller shutter details - as per discharge (24/02/2012)

29.         Site waste management plan - as per discharge (24/02/2012)

30.         Post construction Review - Submission of details within 6 months

31.         Development phasing - as per discharge (07/03/2012)

32.         10% renewable energy – Submission of details within 6 months

33.         Public Art - as per discharge (30/05/2013)

34.         External lighting - as per discharge (07/03/2012)

 

(b)That, in order to give proper effect to the Committee’s intentions and without changing the substance of the decision, authority be delegated to the Principal Planning Manager, in consultation with the Chairman (or in her absence the Vice Chairman) of Southern Planning Committee, to correct any technical slip or omission in the wording of the resolution, between approval of the minutes and issue of the decision notice.

 

Informative:

 

The applicant to consider the establishment of a residents’ liaison group regarding deliveries.

 

Supporting documents: