To consider the above planning application.
Minutes:
The Committee considered a report regarding the above planning application and a written update.
RESOLVED
(a) That the application be REFUSED for the following reasons:
1. The proposed residential development is unsustainable because it is located within the Open Countryside, contrary to Policies NE.2 (Open Countryside) and RES.5 (Housing in Open Countryside) of the Borough of Crewe and Nantwich Replacement Local Plan, Policy PG 5 of the Cheshire East Local Plan Strategy – Submission Version and the principles of the National Planning Policy Framework and create harm to interests of acknowledged importance. The Local Planning Authority can demonstrate a 5 year supply of housing land in accordance with the National Planning Policy Framework. As such the application is also contrary to the emerging Development Strategy. Consequently, there are no material circumstances to indicate that permission should be granted contrary to the development plan.
2. In the opinion of the Local Planning Authority, the proposed development would cause a significant erosion of the Green Gap between the built up areas of Shavington and Crewe and would adversely affect the visual character of the landscape which would significantly and demonstrably outweigh the benefits of the scheme notwithstanding a shortfall in housing land supply. The development is therefore contrary to Policy NE4 (Green Gaps) of the Borough of Crewe and Nantwich Replacement Local Plan 2011 and guidance contained within the NPPF.
3. Insufficient information has been submitted with the application to determine if the proposal would involve the removal of an “important” hedgerow as defined in the Hedgerow Regulations 1997. As the Local Planning Authority can demonstrate a 5 year supply of housing land there are overriding reasons for allowing the development. Therefore the scheme is contrary to Policy NE.5 OF THE Borough of Crewe and Nantwich Replacement Local Plan 2011 and guidance contained within the NPPF.
4. Insufficient information has been submitted to demonstrate that this development together with other committed development in Shavington would not have a severe impact upon the local highway network. As a result the proposed development would be contrary to Policy BE.3 (Access and Parking) of the Borough of Crewe and Nantwich Replacement Local Plan 2011 and the NPPF.
(b) That, in order to give proper effect to the Committee’s intentions and without changing the substance of the decision, authority be delegated to the Principal Planning Manager, in consultation with the Chairman (or in her absence the Vice Chairman) of Southern Planning Committee, to correct any technical slip or omission in the wording of the resolution, between approval of the minutes and issue of the decision notice.
(c) That, should this application be the subject of an appeal, authority be delegated to the Principal Planning Manager in consultation with the Chairman of the Southern Planning Committee to enter into a planning agreement in accordance with the S106 Town and Country Planning Act to secure the Heads of Terms for a S106 Agreement.
S106 Heads of Terms:
1. A scheme for the provision of 30% affordable housing – 65% to be provided as social rent/affordable rent with 35% intermediate tenure. The scheme shall include:
- The numbers, type, tenure and location on the site of the affordable housing provision
- The timing of the construction of the affordable housing and its phasing in relation to the occupancy of the market housing
- The arrangements for the transfer of the affordable housing to an affordable housing provider or the management of the affordable housing if no Registered Social Landlord is involved
- The arrangements to ensure that such provision is affordable for both first and subsequent occupiers of the affordable housing; and
- The occupancy criteria to be used for determining the identity of occupiers of the affordable housing and the means by which such occupancy criteria shall be enforced.
2. Provision of POS and a LEAP with 5 pieces of equipment and a scheme of management.