RESOLVED - That authority be DELEGATED to the Interim Planning and Place Shaping Manager in consultation with the Chairman to APPROVE the application for the reasons set out in the report, subject to:
(a) further consideration being given to the retention of the storage building, as requested by English Heritage.
(b) the following conditions:
1. Standard
2. Plans
3. Materials
4. Surfacing Materials
5. Drainage details to be submitted and agreed in writing
6. Landscaping details to be submitted and agreed in writing
7. Landscaping Implemented
8. Details of External Lighting to be submitted and agreed in writing
9. Details of a construction management plan to include the following:
- details of construction and demolition waste management;
- details of pollution prevention;
- details of any lighting scheme proposed during construction. (Note: lighting should be directed away from the designated sites);
- details of site access, working and safety zones, together with temporary fencing proposals for the site access and site perimeter:
- all contractors working on site should be made aware of and should be provided with a map that clearly shows the boundaries of the Peckforton Woods SSSI in relation to the development site.
10. Details of mortar mix and pointing technique to be submitted and agreed in writing
11. All air vents and grills to be painted black and thereafter retained
12. All external windows to be single glazed unless otherwise agreed in writing
13. Details of cleaning mechanism of stonework
14. Details to be submitted and agreed with approach to blown and damaged stonework
15. All plaster to be lime based unless otherwise agreed in writing
16. Describe and illustrate all replacement/new doors and windows
17. Describe and illustrate proposed new radiators
18. Rainwater goods to be cast iron and painted black unless otherwise agreed in writing
19. Car parking spaces
20. Survey for breeding birds
21. Features for birds
22. Noise survey to be submitted and agreed in writing
23. Contaminated land survey
24. Details of Levels
25. Details of window/door Reveals to be submitted and agreed in writing
26. Details of Service Routes
27. Wardens Accommodation
28. Full details of the construction methods of the all footpaths and access road to be submitted and agreed in writing
Informative:
The applicant is advised that they have a duty to adhere to the regulations of Part IIA of the Environmental Protection Act 1990, the National Planning Policy Framework 2012 and the current Building Control Regulations with regards to contaminated land. If any unforeseen contamination is encountered during the development, the Local Planning Authority (LPA) should be informed immediately. Any investigation / remedial / protective works carried out in relation to this application shall be carried out to agreed timescales and approved by the LPA in writing. The responsibility to ensure the safe development of land affected by contamination rests primarily with the developer.