13/4442C Saxon Cross Motel, Holmes Chapel Road, Sandbach CW11 1SE: Variation of condition 5 on approval 11/2018C - Demolition of Existing Hotel on the Site. Change of Use from a Category C1 Development to a Mixed Use of Category B1 and B8. Construction of a Single-Storey Office Building and Warehouse Building. New Hard Landscaping Associated with the Proposed Development, Including Relocation of Vehicular Access for Jonathan Bolshaw, Bolshaw Industrial Powders

To consider the above planning application.

Minutes:

Note: Councillor D Newton left the meeting and returned during consideration of this item but after returning did not take part in the debate or vote.

 

The Committee considered a report regarding the above planning application.

 

RESOLVED

 

(a)    That, for the reasons set out in the report, the application be APPROVED subject to the following conditions:

 

1. Standard time limit 3 years from 5th August 2011

2. Materials to be submitted to the LPA and approved in writing

3. Surfacing materials in accordance with plan reference AD1991.12

4. Development in accordance with the Contaminated Land Assessment. Details of clean cover to be provided.

5. Condition to specify the approved plans

6. The car/HGV parking shown on the approved plans to be provided before the unit hereby approved is first occupied

7. Cycle parking facilities in accordance with plan reference AD1991.10

8. Shower facilities to be in accordance with plan reference AD1991.14

9. Drainage details to be in accordance with plan reference AD1991.13A

10. Details of oil interceptors to be submitted to the LPA and approved in writing

11. External lighting to be in accordance with plan reference AD1991.15A

12. No external storage

13. Bin Storage details to be in accordance with plan reference AD1991.11

14. Landscaping to be in accordance with plan reference AD1991.09A

15. Landscaping to be completed

16. The hours of construction (and associated deliveries to the site) of the development shall be restricted to 08:00 to 18:00 hours on Mondays to Fridays, 08:00 to 13:00 hours on Saturdays, with no work at any other time including Sundays and Public Holidays.

17. Details of any pile driving to be submitted to the LPA and approved in writing

18. Prior to the development coming into use, the applicant shall submit to the local planning authority a travel plan demonstrating how they will ensure that vehicle movements associated with the development (staff cars, deliveries and HGV movements) from the site will be managed to ensure that traffic congestion within the air quality management area will not be adversely affected.

19. Prior to first occupation the new access and visibility splays will be constructed to completion in accordance with approved plans

20. Prior to first occupation the existing access will be permanently closed and the highway kerb line reinstated at the edge of carriageway in accordance with plan reference AD1991.16A

21. Prior to any commencement of works between 1st March and 31st August in any year, a detailed survey is required to check for nesting birds. Where nests are found in any building, hedgerow, tree or scrub to be removed (or converted or demolished in the case of buildings), a 4m exclusion zone to be left around the nest until breeding is complete. Completion of nesting should be confirmed by a suitably qualified person and a report submitted to the Council.

22. Breeding Bird Measures in accordance with the plan titles ‘Breeding Bird Ecological Enhancements Figure 1’

23. The proposed development to proceed in accordance with the recommendation made in the submitted Updated Ecological Appraisal dated May 2011 and the submitted letter from fpcr dated 27th June 2011.

 

(b)  That, in the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions/informatives/planning obligations or reasons for approval/refusal) prior to the decision being issued, the Interim Planning and Place Shaping Manager be granted delegated authority to do so in consultation with the Chairman of the Southern Planning Committee, provided that the changes do not exceed the substantive nature of the Committee’s decision.

 

(c)  That, should this application be the subject of an appeal, authority be delegated to the Interim Planning and Place Shaping Manager in consultation with the Chairman of the Southern Planning Committee to enter into a planning agreement in accordance with the S106 Town and Country Planning Act to secure the Heads of Terms for a S106 Agreement.

 