To consider the above planning application.
Minutes:
Note: Councillor P Grovesleft the meeting prior to consideration of this application.
Note: Councillor S Jones (Ward Councillor), Ms J Aspinall (objector) and Mr D Woodfine (on behalf of the applicant) attended the meeting and addressed the Committee on this matter.
The Committee considered a report regarding the above planning application and an oral report of the site inspection.
RESOLVED – That, for the reasons set out in the report, the application be APPROVED subject to the following conditions:
1. Standard time – 3 years
2. External Materials (including a string detail) to be submitted to the LPA and approved in writing
3. The rebuilt gable of the house to be constructed in reclaimed brickwork from the demolished extension and in a bond to match the existing house, to be agreed prior to commencement via sample panel, or in other suitable alternative materials to be submitted to the LPA for approval in writing. Mortar and pointing to also be agreed via the sample panel, also include sample of supplementary bricks for the new dwelling to also be approved and sample panel provided
4. Submission of working details of verge and eaves treatments to be agreed to be designed as semi exposed rafter feet and purlin ends with reduced fascia board
5. Prior to commencement of development, working details at scale of 1:10 of entrance doorways into the retained dwelling and the new build to be submitted
6. A schedule of all windows to be replaced in the retained building, and 1:10 details of all new windows (including sections) to be submitted before commencement. In respect to the new house, 1:10 details of all windows including details of heads and sills.
7. A sustainable design strategy shall be developed as part of the detailed design of the scheme and shall be submitted prior to commencement this shall set out the performance of the development in respect to climate change mitigation and adaptation. This shall focus on building fabric, resource management, the potential for renewable/low carbon energy and in building adaptation measures into the building and landscape design
8. Submission of working details of chimney on new dwelling (1:10)
9. All rainwater goods to be in cast metal, finish to be agreed prior to installation
10. Landscaping Scheme
11. Landscaping to be implemented
12. Tree Protection Measures
13. Implementation of programme of tree works as identified in Arboricultural report.
14. Submission of Arboricultural Method statement to cover a programme of Arboricultural supervision, (including demolition works), no dig ground works within root protection areas and installation of services if within root protection areas.
15. Boundary treatment details to be submitted to the LPA and approved in writing
16. Remove PD Rights for extensions and alterations to the approved dwellings, including garage conversion
17. The hours of construction shall be limited to 08:00 – 18:00 Monday to Friday, 09:00 – 14:00 Saturday and not at all on Sundays or Bank Holidays
18. Pile Foundations operations limited to Monday – Friday 09:00 – 17:30 hrs, Saturday 09:00 – 13:00 hrs, Sunday and Public Holidays Nil and method statement
Note – Contaminated Land