To consider the above planning application.
Additional documents:
Minutes:
Consideration was given to the above planning application.
The following attended the meeting and spoke on the application:
Wilmslow Town Councillor Jon Newall; Councillor Lata Anderson (neighbour ward councillor; Ms Sonia Harrison (objector) and Mr Andy Frost (agent).
RESOLVED:
For the reasons set out in the report, update report and verbal update at the meeting the application be APPROVED subject to the removal of the holding condition from the Environment Agency, the completion of the Section 111/Section 106 agreement to secure:
S106 |
Amount |
Trigger |
Strategic green and common areas including the Local Wildlife site - strategy, management and maintenance plans |
|
Commencement of development |
Strategic green and common areas including the Local Wildlife site – provision and transfer to management company |
|
Prior to disposal of 1000th unit |
Off-site ecological mitigation |
£5,943,664 |
Lump sum prior to commencement and then maintenance sum annually |
Education (primary/secondary/SEN) |
£14,661,362 |
50% prior to Commencement of a unit then 50% prior to occupation of 300th unit |
Education – provision of school site |
|
Prior to commencement of dwellings |
Village Hall/village centre/employment uses-provision of |
|
Prior to disposal of 1000th unit |
Affordable Housing |
30% |
Sale or let of 50% market houses |
Highway Improvement Works |
£5,047,000 |
Prior to occupation of 300 unites |
Highways – Hall Moss Lane |
£387,522 |
Prior to commencement of development |
Highways – Poynton bypass |
£4,661,192 |
Occupation of the 150th unit |
Highways – Bus Services |
£1,714,000 |
Occupation of the 50th unit |
Highways – Handforth P&R |
£980,000 |
Occupation of the 100th unit |
Highways – Pathways and cycleways |
£500,000 |
Commencement of development |
Highways – Travel Plan monitoring |
£10,000 |
Commencement of development |
Public Open Space in housing area – provision of |
|
Occupation of 50% units in phase |
Public Open Space in housing areas – Transfer to management company and maintenance in perpetuity |
|
Occupation of 75% units in phase |
Allotments/Community Orchard – Provision and transfer to management company |
|
Prior to disposal of 750th unit |
Indoor and outdoor sports facilities |
£1,719,987 |
50% prior to occupation of any Units and 50% prior to occupation of 750th unit |
Healthcare – Handforth |
£1,530,015 |
Prior to occupation of any units |
and the following conditions:
OUTLINE
1 Time Limit – submission of reserved matter (5 years)
2 Approval of reserve matters – all reserved
3 Approved Plans – Location and parameter plans
4 Approve Accommodation Schedule
5 Compliance with the EIA (& Addendum) and mitigation
6 No commencement until approved initial primary works complete
7 Approval of phasing plan
8 Development to comply with housing densities identified in the Indicative Masterplan
9 Compliance with Public Rights of Way and 20-Year Walking Route Code
10 Approval of signage for pedestrians and cyclists, to include timings
11 Programme of archaeological work to be agreed
12 No works on the main development site to take place within 100m of the Diary House Farm (Listed Building) site prior to the completion of the stabilisation/repair works
13 Future development of the designs for the site, coding and development going forward, must adhere to the Heritage Design ... view the full minutes text for item 35