Consideration was given to the above planning application.

 

The following attended the meeting and spoke on the application:

Wilmslow Town Councillor Jon Newall; Councillor Lata Anderson (neighbour ward councillor; Ms Sonia Harrison (objector) and Mr Andy Frost (agent).

 

RESOLVED:

 

For the reasons set out in the report, update report and verbal update at the meeting the application be APPROVED subject to the removal of the holding condition from the Environment Agency, the completion of the Section 111/Section 106 agreement to secure:

 

S106

Amount

Trigger

Strategic green and common areas including the Local Wildlife site - strategy, management and maintenance plans

 

Commencement of development

Strategic green and common areas including the Local Wildlife site – provision and transfer to management company

 

Prior to disposal of 1000th unit

Off-site ecological mitigation

£5,943,664

Lump sum prior to commencement and then maintenance sum annually

Education (primary/secondary/SEN)

£14,661,362

50% prior to Commencement of a unit then 50% prior to occupation of 300th unit

Education – provision of school site

 

Prior to commencement of dwellings

Village Hall/village centre/employment uses-provision of

 

Prior to disposal of 1000th unit

Affordable Housing

30%

Sale or let of 50% market houses

Highway Improvement Works

£5,047,000

Prior to occupation of 300 unites

Highways – Hall Moss Lane

£387,522

Prior to commencement of development

Highways – Poynton bypass

£4,661,192

Occupation of the 150th unit

Highways – Bus Services

£1,714,000

Occupation of the 50th unit

Highways – Handforth P&R

£980,000

Occupation of the 100th unit

Highways – Pathways and cycleways

£500,000

Commencement of development

Highways – Travel Plan monitoring

£10,000

Commencement of development

Public Open Space in housing area – provision of

 

Occupation of 50% units in phase

Public Open Space in housing areas – Transfer to management company and maintenance in perpetuity

 

Occupation of 75% units in phase

Allotments/Community Orchard – Provision and transfer to management company

 

Prior to disposal of 750th unit

Indoor and outdoor sports facilities

£1,719,987

50% prior to occupation of any Units and 50% prior to occupation of 750th unit

Healthcare – Handforth

£1,530,015

Prior to occupation of any units

 

and the following conditions:

 

OUTLINE

 

1          Time Limit – submission of reserved matter (5 years)

2          Approval of reserve matters – all reserved

3          Approved Plans – Location and parameter plans

4          Approve Accommodation Schedule

5          Compliance with the EIA (& Addendum) and mitigation

6          No commencement until approved initial primary works complete

7          Approval of phasing plan

8          Development to comply with housing densities identified in the Indicative Masterplan

9          Compliance with Public Rights of Way and 20-Year Walking Route Code

10       Approval of signage for pedestrians and cyclists, to include timings

11       Programme of archaeological work to be agreed

12       No works on the main development site to take place within 100m of the Diary House Farm (Listed Building) site prior to the completion of the stabilisation/repair works