10/0692W-To carry out Development without Complying with Conditions Attached to 7/P05/1326 to Extend the Operation Life of the Maw Green Landfill Facility to 31 December 2017, Restoration by 31 December 2018, permit a Variation to the Sequence of Pha

Meeting: 04/12/2013 - Strategic Planning Board (Item 120)

120 10/0692W-To carry out Development without Complying with Conditions Attached to 7/P05/1326 to Extend the Operation Life of the Maw Green Landfill Facility to 31 December 2017, Restoration by 31 December 2018, permit a Variation to the Sequence of Phasing of Operations along with Minor re-contouring to the South East of the Site, Maw Green Landfill Site, Maw Green Road, Crewe for 3C Waste Ltd pdf icon PDF 249 KB

To consider the above application.

Minutes:

Consideration was given to the above application.

 

RESOLVED

 

That for the reasons set out in the report and in the oral update to Board and subject to receiving confirmation from the Property Portfolio Manager that they have noted the reliance being placed on the legal easement to enter the Phase 1 land for the purposes of carrying out gas and leachate monitoring/maintenance the recommendation for approval should be maintained as per the Strategic Planning Board committee report dated 2June 2010; subject to:

(1)       Deed of variation to the existing Section 106 Planning Obligation to the extent described in the report to secure:

-       diversion and maintenance in perpetuity Fowle Brook;

-       long-term management of the restored nature conservation area on Cell 9a for a period of 15 years following the restoration of Cell 9a

-       monitoring and maintenance of the leachate control system;

-       monitoring the generation and extraction of landfill gas;

-       Heavy Goods Vehicle routing; and

-       Maintenance and management of a length of Maw Green Road.

 

(2)       Planning permission being granted subject to conditions covering in particular: - 

-       All the conditions attached to permission 7/P05/1326 unless amended by those below;

-       Approved plans;

-       Revisions to existing approved restoration plan – replace with in interim and final restoration plan and associated restoration conditions;

-       Revisions to existing phasing plans and associated phasing conditions;

-       Revisions to existing pre-settlement contours, and associated contouring conditions;

-       Additional surface water lagoon plan;

-       Extension of time to 31st December 2017 with interim restoration of the site within 12 months or no later than 31st December 2018

-       Final restoration as final restoration plan to be no later than 12 months following the cessation of production of leachate and landfill gas;

-       Interim and final restoration proposals to be amended to include rough tussocky grassland to provide suitable habitat for breeding skylarks;

-       Approved Method statement for protected species;

-       Liaison Committee Scheme;

-       Noise limits;

-       Noise Monitoring Scheme;

Best practical site management for noise/ dust/ odour/ flies/ vermin/ birds/ litter control as per ES.