To consider the above application.
Minutes:
Consideration was given to the above application.
RESOLVED
That for the reasons in the update report to Board, the application be approved subject to the following conditions:-
1. Submission of details of layout, scale, appearance access to all individual plots and landscaping.
2. Application for reserved matters to be made within 3 years of date of this permission.
3. Development to be implemented within 3 years of the date of this outline permission or expiry of 2 years from final approval of the last of the reserved matters.
4. All reserved matters applications to include site survey and details of proposed site and slab levels
5. All reserved matters applications to include Framework Travel Plan, to be followed by a travel plan and its implementation.
6. All reserved matters applications to provide development based on the all the sustainable development principles of the Design and Access Statement
7. Car parking, motorised cycle parking and covered secure cycle parkingfor each plot, with showers in each building for use by all staff.
8. Site to be used for B1 office use only.
9. Remedial tree works to be completed in accordance with tree survey and recommendations of ecological survey.
10. Replacement planting for trees which are removed to be provided with first reserved matters application. To include details of species, size on planting, location and timetable for the provision of the tree planting.
11. Details of tree protection to be submitted approved and implemented.
12. Landscaping scheme to be submitted with the first reserved matters planning application for the site to incorporate strategic planting to the University Way frontage and the planting on the north side of building B and south side of building D to reflect the strategic planting on Area C to the south of this site.
13. Final check of trees for bats prior to tree works.
14. Protection for nesting birds.
15. No development within 30m of any badger sett and further survey with mitigation if necessary to ensure protection to any setts.
16. Scheme for the provision of a wildlife buffer to the Valley Brook and Englesea Brook to be submitted approved and implemented.
17. Use of native species in landscaping of all plots.
18. Minimum slab level of 49.79m AOD for all buildings.
19. Pedestrian access to all buildings to be minimum of 49.49m AOD
20. Scheme for surface water regulation of the site to be submitted with first reserved matters for the development, approved and implemented.
21. Scheme for the disposal of surface and foul water drainage to be submitted approved and implemented with each plot.
22. Oil interceptors to car parks.
23. Areas used for vehicle washing to be contained and connected to foul sewer.
24. Scheme for protection of Englesea Brook and Valley Brook from contamination by building materials to be submitted approved and implemented.
25. Maximum floor area.
26. Details of external lighting.
27. Control invasive species on the site.
Members of the Strategic Board expressed the desire to see ... view the full minutes text for item 61