12/1799C-Importation of inert material to install cover system to former tip and restoration scheme to allow change of use to informal recreational open space with ancillary car park, Former Tip, Roughwood Lane, Hassall Green, Sandbach, Cheshire for

Meeting: 14/08/2013 - Strategic Planning Board (Item 56)

56 12/1799C-Importation of inert material to install cover system to former tip and restoration scheme to allow change of use to informal recreational open space with ancillary car park, Former Tip, Roughwood Lane, Hassall Green, Sandbach, Cheshire for Hays Plc pdf icon PDF 430 KB

To consider the above application.

Minutes:

(Councillor J Wray arrived back to the meeting as the application was being presented and therefore did not take part in the debate or vote on the application).

 

Consideration was given to the above application.

 

(Caroline Ridge, the agent for the applicant and David Rix, the Consultant for the applicant attended the meeting and spoke in respect of the application).

 

RESOLVED

 

That for the reasons set out in the report the application be approved subject to the following conditions:-

1.     Standard conditions

2.     Control over type and amount of material to be imported

3.     No processing of materials on site

4.     Scheme to control dust

5.     Implementation of remediation/protection measures and provision of site completion statement

6.     Methods to address any unexpected contamination on site

7.     Hours of operation

8.     Restriction on overall HGV movements and daily movements

9.     Provision of temporary road signs

10.Method statement for regulating vehicle movements

11.Facilities to prevent deposit of extraneous material on highway

12.Provision of wheelwash

13.Entrance gate to remain locked aside from when in use by visiting parties

14.No external lighting

15.Fencing to be installed for defensive planting

16.Badger mitigation measures

17.Provisions to safeguard nesting birds

18.Scheme of measures for detailed stabilisation works

19.Provision of full tree survey prior to works commencing on site

20.Provision of full tree protection measures

21.Full landscape restoration scheme