Issue - meetings

12/4652M-Erection of Class A1 retail store with conservatory, garden centre, ancillary coffee shop and associated car parking, Land off Earl Road, Handforth, Cheshire for Next PLC

Meeting: 14/08/2013 - Strategic Planning Board (Item 58)

58 12/4652M-Erection of Class A1 retail store with conservatory, garden centre, ancillary coffee shop and associated car parking, Land off Earl Road, Handforth, Cheshire for Next Plc pdf icon PDF 562 KB

To consider the above application.

Minutes:

Consideration was given to the above application.

 

(Adrian Trotter, the agent for the applicant attended the meeting and spoke in respect of the application).

 

RESOLVED

 

That for the reasons set out in the report and in the update to Board, the application be delegated back to the Planning & Place Shaping Manager in consultation with the Chairman of the Strategic Planning Board for approval subject to referral to the Secretary of State, subject to the completion of a Section 106 Agreement securing the following broad Heads of Terms:-

 

 

  • Payment of a Commuted sum for off-site provision of Public Open Space for improvements, additions and enhancement of existing Public Open Space facilities at open space facilities at Meriton Road Park, Henbury Road and Spath Lane.

·       Payment of a commuted sum for off-site provision of recreation/outdoor sport (outdoor sports facilities and pitches, courts, greens and supporting facilities/infrastructure) at Meriton Road Park and Spath Lane

  • Submission, operation and monitoring of a staff travel plan

·       Payment of a commuted sum for improvements to footpaths / creation of cycleways

·       Payment of a commuted sum for improvements to local bus services to and from the site

·       Payment of commuted sum towards or provision of an electric car charging point.

·       Payment of a commuted sum for infrastructure works within the employment site

·       Submission of an employment and skills plan (local employment agreement)

 

And subject to the following conditions:-

 

  1. Commencement of development (3 years)
  2. Development in accordance with approved plans
  3. Submission of samples of building materials
  4. Development in accordance with Flood Risk Assessment
  5. Site to be drained on a separate system
  6. Phase 2 contaminated land survey to be submitted
  7. Landscaping-submission of details
  8. Landscaping (implementation)
  9. Electric car charging points to be provided
  10. No subdivision of retail unit
  11. Provision of cycle parking shown on approved plans
  12. The building hereby approved shall be constructed to achieve a minimum rating of BREEAM ‘very good’ as outlined in the sustainability assessment
  13. Details of external lighting to be submitted for approval