To consider the above planning application.
Minutes:
The Committee considered a report regarding the above planning application and a written update.
RESOLVED – That, for the reasons set out in the report, the application be APPROVED subject to the following conditions:
1. Standard 3 year time limit
2. Compliance with approved plans
3. Submission and approval of materials
4. Submission and approval of cycle parking within scheme
5. Submission and approval of contaminated land mitigation measures
6. Dust control measures
7. Piling hours to be restricted
8. Piling method Statement
9. Submission and approval of external lighting details
10. Construction Hours to be restricted
11. Bin Storage
12. Submission and approval of boundary treatment
13. Submission and approval of noise mitigation measures
14. Submission and approval of landscaping
15. Implementation of landscaping
16. Provision of Parking
17. Access works to be carried out prior to first occupation
18. Affordable Housing
19. Tree Protection
20. Implementation of Tree protection
21. Special construction measures under trees
22. No surface water, only foul water to discharge to sewer
23. Submission of scheme of drainage