Issue - meetings

12/1157N-Variation of Conditon 14 of application P03/1071 Relating to the Proposed Rail Link, Land off Crewe Road, Basford West, Crewe for Goodman

Meeting: 14/11/2012 - Strategic Planning Board (Item 96)

96 12/1157N-Variation of Conditon 14 of application P03/1071 Relating to the Proposed Rail Link, Land off Crewe Road, Basford West, Crewe for Goodman pdf icon PDF 1 MB

To consider the above application.

Minutes:

The Committee considered a report regarding the above planning application.

 

Mr David Rolinson, Agent for the Applicant attended the meeting and spoke in respect of the application

 

RESOLVED:

 

That, for the reasons set out in the report, the application be APPROVED subject to:

 

  1. Deed of Variation to Section 106 Agreement attached to the planning permission P03/1071 to make provision for the following:
    • Provision of rail links from the main line to the application site to be provided prior to the development of rail linked units (Phase 3).  The trigger being at 4,645 sq m B1 development, 18,580 sq m B2/B8 development and 47,844 sq m B8 development.
    • Should the rail link not be provided then an additional highways contribution of £524,040.60 (index linked to the date of the original S106) will be payable.
    • This contribution will be put towards highway improvements to the Strategic A500 corridor and/or Gresty Road/South Street Corridor.
    • Travel Plan to make provision for, if the rail link is provided, the maximum trip generation for the whole site to be constrained to 861 vehicles and if the rail link is not provided as part of phase 3 of the scheme, then the maximum total Basford West traffic generation is constrained to 1003 vehicles

 

  1. The following conditions:

 

1-3. Standard outline conditions to include 10 years for the submission of reserved matters, including details of “landmark features”.

4. Amended plans

5. The phasing of the development to be as given in drawings 2000-068/024 C except that the spine road to be constructed in its entirety in phase 1.

6. Uses of land and principles of development in accordance with each character area to be as shown on drawing 2000-068/025B except that building heights shall comply with limitations set in Basford West Development Brief.

7. Floor spacing not to exceed the limits of each character area as given on drawing 2000-068/025B

8. No development to commence which exceeds 25% floor area (i.e. 4,645 sq m of B1 floor space and 22,868 sq m of B8 floor space) to commence until scheme for works at junction 16 of M6 submitted and agreed.

9. No development to be brought into use, which exceeds 4,645 sq m of B1 floor space and 22,868 sq m of B8 floor space before works approved under the above condition in relation to junction 16 of M6 have been implemented.

10. Development not to exceed 4,645 sq m B1 offices, 18,580 sq m B2 and 120, 770 sq m B8 development at any time.

11. Reserved matters applications to include cross sections through the site and details of existing and proposed levels to demonstrate impact of the proposed development on the locality.

12. Provision of spine road in phase 1, remaining roads in accordance with phasing plan, all in accordance with drawings to be submitted and approved. 

13. Landscape scheme for spine road including street furniture and public art, to be submitted and approved prior to commencement of construction of spine road.

14. Scheme  ...  view the full minutes text for item 96