Issue - meetings

12/1593M - Oaklands Community Infant School, Tudor Road, Wilmslow, Cheshire SK9 2HB: Variation of Conditions 2 and 24 Attached to Permission 12/0027M to Enable Development to Commence Prior to the Installation of the Toucan Crossing to Dean Row Road

Meeting: 13/06/2012 - Northern Planning Committee (Item 14)

14 12/1593M - Oaklands Community Infant School, Tudor Road, Wilmslow, Cheshire SK9 2HB: Variation of Conditions 2 and 24 Attached to Permission 12/0027M to Enable Development to Commence Prior to the Installation of the Toucan Crossing to Dean Row Road and to Provide Additional Velux Windows within the Proposed Dwellings pdf icon PDF 444 KB

To consider the above planning application.

Minutes:

The Committee considered a report regarding the above planning application, a site layout plan and an oral report by the Planning Officer.

 

RESOLVED

 

That for the reasons set out in the report, the application be APPROVED subject to

 

(a)   the completion of an updated Section 106 Agreement to secure:

 

·         Provision of affordable housing provision on site in the form of 6 x 2 bed units, which are made up of 4 units for social rent and 2 units for intermediate tenure.

·         Provision of commuted sum in lieu of on site provision of play and amenity - £63,000.

·         Provision of commuted sum in lieu of on site provision of Recreation/Sport - £15,000; and

 

(b)  The following conditions:

 

1.    Landscaping - submission of details                                                                                                                                                                                                                            

2.    Tree retention                                                                                                                                                                                                                                                 

3.    Tree protection                                                                                                                                                                                                                                                

4.    Commencement of development (3 years)                                                                                                                                                                                                                          

5.    Vehicular visibility at access (dimensions)                                                                                                                                                                                                                    

6.    Construction specification/method statement                                                                                                                                                                                                                    

7.    Development in accord with revised plans (numbered)                                                                                                                                                                                                            

8.    Landscaping (implementation)                                                                                                                                                                                                                                   

9.    Details of materials to be submitted                                                                                                                                                                                                                           

10.Protection for breeding birds                                                                                                                                                                                                                                  

11.Submission of construction method statement                                                                                                                                                                                                                   

12.no dormers other than authorised                                                                                                                                                                                                                               

13.levels details to be submitted                                                                                                                                                                                                                                 

14.open plan estate layout only                                                                                                                                                                                                                                   

15.removal of permitted development rights plots 1.3,6

16.Toucan crossing to be Operational by 1 Feb 2013 and construction access method statement  to be submitted approved and implemented

17.10% renewable energy provision                                                                                                                                                                                                                                 

18.contaminated land assessment