Ms A Snook (on behalf of Persimmon Homes North
West - the agent) attended the meeting and addressed the Committee
on this matter.
The Committee considered a report regarding
the above planning application, a written update and an amended
plan.
RESOLVED
To grant DELEGATED POWERS to the Development
and Building Control Manager, in consultation with the Chairman, to
APPROVE the application subject to a period of re-consultation on
the amended plans and no new issues being raised and subject
to:
(a) The prior signing of a Section 106
agreement to secure:
- 19 affordable units split on the
basis of 12 affordable rent and 7 intermediate tenure (comprising 4
x 2 bed and 8 x 3 bed for affordable rent and 7 x 3 bed for
intermediate tenure) to be made affordable in perpetuity, units to
be tenure blind and pepper potted. All
units to be provided by occupation of 30th open market
unit; Affordable rent to be provided through a Registered
Provider.
- £21,152.67 for the upgrading
of an existing children’s play facility at Moss Drive (not be
‘time limited’).
- Provision for a management company
to maintain the on-site amenity space in perpetuity.
(b) And the
following conditions:
- Standard.
- Plans.
- First Floor window in east gable of
Plot 3 to be obscured glazed.
- Contaminated land
investigation.
- Submission and approval of external
lighting.
- Hours of construction.
- Details of pile driving
operations.
- Submission of details of bin
storage.
- Scheme to manage the risk of
flooding.
- Scheme to limit surface water
runoff.
- Discharge of surface water to mimic
that of the existing site.
- Sustainable Urban Drainage
System.
- Site to be drained in accordance
with submitted statement. All surface
water to go to soakaway/watercourse.
Only foul drainage to be connected to sewer.
- Provision of bat and bird nest
boxes.
- Retention of important trees.
- Submission of Comprehensive tree
protection measures.
- Implementation of Tree
Protection.
- Timing of the works and details of
mitigation measures to ensure that the development would not have a
detrimental impact upon breeding birds.
- Hedgerows to be enhanced by
‘gapping up’ as part of the landscaping scheme for the
site.
- Development to proceed in accordance
with proposed Great Crested Newt mitigation measures.
- Implementation of Landscaping
Scheme.
- Submission/approval and
implementation of materials.
- Submission/approval and
implementation of access construction details.
- Provision of car parking.
- Submission/approval and
implementation of revised scheme of Boundary treatment.
- Construction Management Plan shall
be agreed prior to the commencement of development.
In
the event of any changes being needed to the wording of the
Committee’s decision (such as to delete, vary or add
conditions/informatives/planning
obligations or reasons for approval/refusal) prior to the decision
being issued, the Head of Development Management and Building
Control has delegated authority to do so in consultation with the
Chairman of the Strategic Planning Board, provided that the changes
do not exceed the substantive nature of the Committee’s
decision.
During
consideration of this item, Councillor Bailey arrived to the
meeting, but did not take part in the debate or vote.