120 11/4110M - Disley Tissue Ltd, Waterside Road, Disley, Stockport, Cheshire SK12 2HW
PDF 839 KB
To consider the above planning
application.
Minutes:
Councillor D Kidd (on behalf of Disley Parish Council) had not registered his
intention to address the Committee.
However, in accordance with paragraph 2.8 of the public speaking
rights at Strategic Planning Board and Planning Committee meetings,
the Committee agreed to allow Councillor Kidd to speak.
Councillor D Kidd (on behalf of Disley Parish
Council), Mrs J Richards (an objector) and Mr T Partridge (the
agent) attended the meeting and addressed the Committee on this
matter.
The Committee considered a report regarding
the above planning application, a written update and an oral report
of the site inspection.
RESOLVED
That the application be APPROVED subject to
the following conditions:
- Commencement of development (3
years).
- Development in accord with approved
plans.
- Tree retention.
- Tree protection.
- Tree pruning/felling
specification.
- Landscaping – revision to
include woodland belt and replacement woodland planting area, to
include a substantial proportion of larger planting stock (such as
20% containerised stock of a girth not less than 12 cms or equivalent) in order to achieve immediate
impact and rapid establishment of semi mature trees.
- Landscaping (implementation).
- Submission of landscape management
plan.
- Submission of landscape/woodland
management plan.
- Colour and materials for the
building elevations and roofs shall be agreed prior to the
commencement of development with the Local Planning Authority.
- Programme of archaeological work in
accordance with written scheme of investigation.
- Protection from noise during
construction/Demolition (hours of construction).
- Hours of construction for Pile
Foundations limited.
- Hours of construction for Floor
Floating (polishing large surface wet concrete floors) to be
agreed.
- Deliveries to the site may follow
weighbridge hours – subject to using Lower Hague Road
only.
- Compliance monitoring of acoustic
amelioration in accordance with Acoustic Report.
- Air quality mitigation measures to
be carried out in accordance with the Environmental Statement.
- Submission and implementation of
approved Remediation Statement and associated works.
- Prevention of contamination into
watercourse.
- Verification of remediation
strategy, to prevent contamination of watercourse.
- The flue stack shall be fitted with
an obstacle warning light for the purposes of aviation safety.
- Ecological Management Plan to be
agreed and finalised within 3 months of granting of planning
permission.
- Protection of breeding birds.
- Development shall be carried out in
full accordance with the Site Waste Management Plan
recommendations.
- Development shall be carried out in
full accordance with the Flood Risk Assessment
recommendations.
- Development shall be carried out in
full accordance with the Travel Plan recommendations.
- Prior to the commencement of
development, a Community Liaison Group shall be formed, details of
which shall be submitted to and approved by the LPA.
- Development shall not commence until
directional signage has been erected at the top of Waterside Road,
indicating the location of the site access for delivery/collection
vehicles.