Crewe Green Link Road: Network Rail Land Negotiations

To consider a report seeking approval to proceed with the agreements required with Network Rail to acquire the necessary rights and land to construct the Crewe Green Link Road (South) highway scheme.

Minutes:

The report sought approval to proceed with the agreements required with Network Rail to acquire the necessary rights and land to construct the Crewe Green Link Road (South) highway scheme. This included any ancillary agreements with Network Rail that may be required

 

RESOLVED

 

That the Network Rail land agreement be progressed on the terms set out in the report, and the terms of any ancillary agreements required with Network Rail to deliver the scheme, including those required by Network Rail for Asset protection and future maintenance of the completed structure, be determined by the Strategic Director Places, Head of Highways & Transport, Borough Solicitor and Asset Manager.