11/1165N Station Yard, Wrenbury Road, Wrenbury CW5 8HA: Outline Planning Permission With All Matters Reserved For Sixteen Local Affordable Houses for Mr Trevor Bates

Meeting: 07/12/2011 - Southern Planning Committee (Item 117)

117 11/1165N Station Yard, Wrenbury Road, Wrenbury CW5 8HA: Outline Planning Permission With All Matters Reserved For Sixteen Local Affordable Houses for Mr Trevor Bates pdf icon PDF 460 KB

To consider the above planning application.

Minutes:

Note: Having exercised his separate speaking rights as a Ward Councillor, Councillor S Davies withdrew from the meeting during consideration of this item.

 

Note: Mr Barlow (objector), Mr M Banks(supporter) and Mr T Bates (applicant) attended the meeting and addressed the Committee on this matter.

 

The Committee considered a report regarding the above planning application, a written update, an oral update and an oral report of the site inspection by the Principal Planning Officer.

 

RESOLVED – That the Head of Development be granted delegated authority to APPROVE, subject to:

 

(a)  No objection from United Utilities, Network Rail and HM Railways Inspectorate

 

(b)  The completion of a legal agreement to secure the development as affordable housing in perpetuity

 

(c)  the following conditions:

 

1.         Standard outline time limit

2.         Submission of reserved matters

3.         Approved Plans

4.         No approval of indicative layout

5.         Implementation of noise mitigation measures

6.         Submission / approval and implementation of external lighting

7.         Construction hours limited to Monday – Friday      08:00hrs – 18:00hrs Saturday 09:00hrs – 14:00hrs With no Sunday or Bank Holiday working

8.         Piling restricted to Monday – Friday 08:30hrs – 17:30hrsSaturday 09:30hrs – 14:00hrs, Sunday Nil

9.          “Floor floating” restricted to Monday – Friday         07:30hrs – 20:00hrs, Saturday 08:30hrs – 14:00hrs, Sunday Nil

10.      Submission / approval and implementation of contamination report / mitigation.

11.      Materials

12.      Remove permitted development rights – extensions and ancillary buildings

13.      Submission / approval and implementation of access construction details

14.      Provision of parking to be 200% plus 5 visitor spaces

15.      Submission of Landscaping scheme

16.      Implementation / maintenance of landscaping

17.      Submission / approval and implementation of boundary treatment to include, inter alia, 1.8m palisade fencing to railway and acoustic fencing

18.      Submission / approval and implementation of drainage scheme

19.      Submission / approval and implementation of bat foraging area in the South East corner of the site

20.      No works within bird nesting season unless survey / mitigation submitted and approved

21.      Any future reserved matters application to be supported by an updated badger survey report to include updated mitigation/compensation proposals