To consider the above planning application.
Minutes:
Note: Having exercised his separate speaking rights as a Ward Councillor, Councillor S Davies withdrew from the meeting during consideration of this item.
Note: Mr Barlow (objector), Mr M Banks(supporter) and Mr T Bates (applicant) attended the meeting and addressed the Committee on this matter.
The Committee considered a report regarding the above planning application, a written update, an oral update and an oral report of the site inspection by the Principal Planning Officer.
RESOLVED – That the Head of Development be granted delegated authority to APPROVE, subject to:
(a) No objection from United Utilities, Network Rail and HM Railways Inspectorate
(b) The completion of a legal agreement to secure the development as affordable housing in perpetuity
(c) the following conditions:
1. Standard outline time limit
2. Submission of reserved matters
3. Approved Plans
4. No approval of indicative layout
5. Implementation of noise mitigation measures
6. Submission / approval and implementation of external lighting
7. Construction hours limited to Monday – Friday 08:00hrs – 18:00hrs Saturday 09:00hrs – 14:00hrs With no Sunday or Bank Holiday working
8. Piling restricted to Monday – Friday 08:30hrs – 17:30hrsSaturday 09:30hrs – 14:00hrs, Sunday Nil
9. “Floor floating” restricted to Monday – Friday 07:30hrs – 20:00hrs, Saturday 08:30hrs – 14:00hrs, Sunday Nil
10. Submission / approval and implementation of contamination report / mitigation.
11. Materials
12. Remove permitted development rights – extensions and ancillary buildings
13. Submission / approval and implementation of access construction details
14. Provision of parking to be 200% plus 5 visitor spaces
15. Submission of Landscaping scheme
16. Implementation / maintenance of landscaping
17. Submission / approval and implementation of boundary treatment to include, inter alia, 1.8m palisade fencing to railway and acoustic fencing
18. Submission / approval and implementation of drainage scheme
19. Submission / approval and implementation of bat foraging area in the South East corner of the site
20. No works within bird nesting season unless survey / mitigation submitted and approved
21. Any future reserved matters application to be supported by an updated badger survey report to include updated mitigation/compensation proposals