To consider the above application.
Minutes:
(Councillor J Macrae declared a personal interest in application 11/1879N on the grounds that he was a Board Member of the South Cheshire Chamber of Commerce).
Consideration was given to the above application.
(Councillor D Bebbington, the Ward Councillor; Councillor D Forest, a Parish Councillor; Mr Beard, an objector; Ms Gordon-Preston, an objector and Ms Clarke the agent for the applicant attended the meeting and spoke in respect of the application)
RESOLVED
That the application be approved subject to completion of Section 106 legal agreement securing
1. Provision of education contribution of £398,990
2. Provision of £300,000 towards highway improvements to the Remer
Street corridor
3. Provision of public open space including amenity greenspace and an equipped children's play area conforming to NEAP Standard, to include:
a. A minimum of 8 pieces of equipment,
b. 1.4 metre high bowtop railing surround with two pedestrian access gates and a double leaf vehicular access gate.
c. Railings to be painted green and pedestrian gates to be yellow.
d. Equipment to be predominantly metal, inclusive, and conforming to BS EN 1176.
e. Equipment to have wetpour safer surfacing underneath it, conforming to BS EN 1177.
f. Surfacing between the wetpour to be tarmacadam with precast concrete edging surround.
g. Access paths to gates to be tarmacadam
4. Provision for future management of children’s play areas and amenity greenspace to include transfer to and future maintenance by a private management company.
5. Provision of 35% of the 400 units proposed across the whole site as affordable housing in perpetuity. Provision within Phase A shall be
26 units comprising 11 x 2 beds, 14 x 3 beds and 1 x 4 bed, with the remainder to be provided in Phase B The tenure split within Phase A to be on a 65% social rent, 35% intermediate tenure basis. The mix of house types and tenure for within Phase B (to include key worker housing) to be agreed as part of subsequent reserved matters applications.
6. Travel Plan Monitoring Fee £5000
7. Contribution of £25,000 for the provision of Green Infrastructure within Crewe and the environs of the site.
And subject to the following conditions:-
1. Standard 3 year time limit (Phase A)
2. Standard outline time limit (Phase B)
3. Submission of reserved matters (Phase B)
4. Plans
5. Materials
6. Boundary Treatment
7. Landscaping submission
8. Landscaping implementation
9. Breeding bird survey to be carried out prior to commencement of any works during nesting season
10. Features for use by birds and bats
11. Habitat creation and management plan
12. Design of proposed pond
13. Design and layout of the proposed newt mitigation area including proposals to ensure no public access.
14. Submission of details of bin storage.
15. Archaeology investigation / report
16. Compliance with flood Risk Assessment
17. Restrict surface water run-off
18. Surface water attenuation
19. Minimum Floor Levels
20. Surface Water Regulation Scheme
21. Site to be drained on a separate system
22. Phase II contaminated land investigation ... view the full minutes text for item 62