11/2112M-Demolition of existing buildings and erection of 40 dwellings including parking, public open space, and landscaping, Havannah Mill, Havannah Lane, Eaton, Congleton for Rowland Homes Limited

Meeting: 28/09/2011 - Strategic Planning Board (Item 56)

56 11/2112M-Demolition of existing buildings and erection of 40 dwellings including parking, public open space, and landscaping, Havannah Mill, Havannah Lane, Eaton, Congleton for Rowland Homes Limited pdf icon PDF 666 KB

To consider the above application.

Minutes:

Consideration was given to the above application.

 

(Rawdon Gascoigne, the agent for the applicant attended the meeting and spoke in respect of the application).

 

RESOLVED

 

That the application be approved subject to the completion of a S106 Agreement securing the following:-

 

  • Provision of 12 affordable houses, 6 x 2 bed dwellings for social rent, 6x 3 bed dwellings for intermediate tenure, available through a cascade provision 
  • Highway works relating to the upgrading of Havannah Lane; provision of a public footpath along the length of the road and upgrading of other footpaths crossing the site
  • Provision of Public Open Space maintained by a Management Company
  • Commuted sum of £52,500 in lieu of an on-site LEAP (Locally Equipped Area for Play)  This money will be spent on upgrading the existing LEAP at St. John’s, to the south of the site 
  • Habitat/landscape management plan
  • Management plan for on & off site SBI works

 

And subject to the following conditions:-

 

 

1.     Commencement of development (3 years)                                                                                                                                                                                                                          

2.     Development in accord with approved plans                                                                                                                                                                                                                      

3.     Materials as submitted                                                                                                                                                                                                                                         

4.     Removal of permitted development rights                                                                                                                                                                                                                        

5.     Energy Supply                                                                                                                                                                                                                                                  

6.     Protection of Site of Biological Importance                                                                                                                                                                                                                    

7.     Protection for breeding birds                                                                                                                                                                                                                                  

8.     Implementation of landscaping scheme submitted with application                                                                                                                                                                                                

9.     Landscaping (implementation)                                                                                                                                                                                                                                   

10. Tree retention                                                                                                                                                                                                                                                 

11. Tree protection                                                                                                                                                                                                                                                

12. Tree pruning / felling specification                                                                                                                                                                                                                           

13. Hours of Construction                                                                                                                                                                                                                                          

14. Pile Driving                                                                                                                                                                                                                                                   

15. Contamination Investigation (Env Health)                                                                                                                                                                                                                       

16. Programme of archaeological work to be submitted                                                                                                                                                                                                               

17. Submission of construction method statement                                                                                                                                                                                                                    

18.  Provision of car parking                                                                                                                                                                                                                                       

19. Footpath scheme                                                                                                                                                                                                                                                

20. Disposal and Storage of Refuse/Recyclables                                                                                                                                                                                                                     

21. Details of drainage                                                                                                                                                                                                                                            

22. Surface Water                                                                                                                                                                                                                                                 

23. Provision of bat roosts                                                                                                                                                                                                                                        

24. Protection of SBI during construction phase                                                                                                                                                                                                                 

25. Finished floor levels (Flooding)                                                                                                                                                                                                                               

26. Levels of access roads, parking and pedestrain areas (Flooding)                                                                                                                                                                                                

27. Assessment of contaminants into watercourse                                                                                                                                                                                                                    

28. Remediation strategy                                                                                                                                                                                                                                           

29. Contamination assessments during development

 