11-1982N - Land between Weston Gate Roundabout and the A500, Weston

Meeting: 30/08/2011 - Strategic Planning Board (Item 42)

42 11-1982N - Construction of a Dual Carriageway All Purpose Road Known as Crewe Green Link South (CGLS) on Land Between Weston Gate Roundabout and the A500 Land between Weston Gate Roundabout and the A500, Weston pdf icon PDF 1 MB

Minutes:

(During consideration of the application, Councillor J Wray arrived to the meeting, however he sat in the public gallery and did not take part in the deabte or vote on the application).

 

(Parish Councillor Cornell, representing Basford and Weston Parish Council attended the meeting and spoke in respect of the application.

 

RESOLVED

 

The application should be approved, subject to the agreement of the Health and Safety Executive that the development would not be a safety hazard to the Audley to Crewe gas pipeline and the following conditions:-

 

1.           Standard time 3 years.

 

2.           Development to proceed in accordance with the approved plans

 

3.           Details of gaps and gates in boundary treatment of the road are required in order to allow access to Basford FP1

 

4.           No development shall take place within the area indicated until the applicant, or their agents or successors in title, has secured the implementation of a programme of archaeological work in accordance with a written scheme of investigation which has been submitted by the applicant and approved in writing by the local planning authority. The work shall be carried out strictly in accordance with the approved scheme.

 

5.           Prior to the commencement of development a detailed tree felling/pruning specification shall be submitted to the LPA for approval in writing

 

6.           Prior to the commencement of development a detailed Arboricultural Method Statement shall be submitted and approved by the LPA

 

7.           Prior to the commencement of development a detailed Tree Protection Scheme shall be submitted and approved by the LPA

 

8.           Prior to the commencement of development a detailed Landscaping Scheme (including native species only) shall be submitted and approved by the LPA

 

9.           Implementation of the approved landscaping scheme.

 

10.       Prior to any development commencing a scheme stating the hours of construction shall be submitted to and approved in writing by the Local Planning Authority and shall be implemented in accordance with the approved details.

 

11.       Prior to any development commencing a scheme stating the hours of pile driving shall be submitted to and approved in writing by the Local Planning Authority and shall be implemented in accordance with the approved details.

 

12.       Prior to the development commencing:-

 

a)    An investigation and Risk Assessment shall be carried out to assess the potential risks from land contamination as defined in the supplied geo-environmental risk assessment.

b)    If such investigation and Risk Assessment identifies that remedial/protective measures are required, then a remedial/protection scheme shall be submitted to, and approved by, the Local Planning Authority (LPA) and shall be implemented.

c)     If remedial/protective measures are required, a Site Completion Statement detailing the remedial/protective measures incorporated shall be submitted to, and approved in writing by, the LPA in full prior to use of the development.

13.       Additional noise monitoring to be carried out within one month of the new road becoming operational any additional mitigation measures shall be provided within 3 months of the road becoming operational

 

14.       The GCN mitigation outlined in CGLS GCN Method Statement produced by TEP  ...  view the full minutes text for item 42