To consider the above application.
Minutes:
Consideration was given to the above application.
RESOLVED
That the application be delegated to the Head of Planning and Housing in consultation with the Chairman for approval following expiry of the consultation period, subject to where any significant new comments are received and the content is not dealt with in the report, then in that case the application should be brought back to the committee, subject to the completion of a Section 106 Agreement comprising of the following Heads of Terms:
And subject to the following conditions:-
1. A03FP - Commencement of development (3 years)
2. A02EX - Submission of samples of building materials
3. A01AP - Development in accord with approved plans
4. A22EX - Roofing material
5. A23EX - Roof ridges
6. A21EX - Roof lights set flush
7. A10EX - Rainwater goods
8. A13EX - Specification of bonding of brickwork
9. A12EX - Fenestration to be set behind reveals
10.A20EX - Submission of details of windows
11.A18EX - Specification of window design / style
12.A11EX - Details to be approved
13.A25GR - Obscure glazing requirement
14.A02HA - Construction of access
15.A03HA - Vehicular visibility at access (dimensions)
16.A06HA - Pedestrian visibility at access in accordance plans to be approved
17.A07HA - No gates - new access
18.A12HA - Closure of access
19.A13HA - Construction of junction / highways
20.A15HA - Construction of highways - submission of details
21.A18HA - Construction of footways
22.A24HA - Provision / retention of service facility
23.A26HA - Prevention of surface water flowing onto highways
24.A30HA - Protection of highway from mud and debris
25.A32HA - Submission of construction method statement
26.A01HP - Provision of car parking
27.A07HP - Drainage and surfacing of hardstanding areas
28.A09HP - Pedestrian visibility within car parks etc
29.A12MC - No lighting
30.A17MC - Decontamination of land
31.A01LS - Landscaping - submission of details
32.A04LS - Landscaping (implementation)
33.A12LS - Landscaping to include details of boundary treatment
34.A23MC - Details of ground levels to be submitted
35.A01GR - Removal of permitted development rights
36.A22GR - Protection from noise during construction (hours of construction)
37.A23GR - Pile Driving
38.Surface water drainage system
39.Additional plans regarding levels, details of construction over the River Lily & surface water drainage
40.Protection of River Lily during construction
41.Provision of public access through the site including provision of a pedestrian bridge over the River Lily