To consider the above planning application.
Minutes:
Note: Mr J Bednal (Mill Green No 2 Management Board), Mrs C Speakman (objector), Mr A Thorley (supporter) and Mr C Butt (Agent on behalf of the Applicant) attended the meeting and addressed the Committee on this matter.
The Committee considered a report regarding the above planning application, a written update, an oral report of the site inspection and an oral update by the Southern Area Manager - Development Management.
RESOLVED – That the Head of Planning and Housing be granted delegated authority to APPROVE, subject to no adverse comments being received from the Environment Agency with respect to the Sequential Test submitted by the applicant.
Approval to be subject to the prior completion of a Section 106 agreement to secure the provision of a commuted sum in lieu of affordable housing provision on site (£153,091), to be ringfenced for the Congleton town area,
and the following conditions:
1. Standard
2. Amended plans
3. Age restriction – over 55 years only
4. Submission of Materials
5. Submission of Landscaping
6. Implementation of Landscaping
7. Submission of Tree Protection
8. Implementation of Tree Protection
9. Submission of Arboricultural Method Statement
10. Provision of parking prior to occupation
11. Scheme of Drainage to be submitted and approved
12. No building over sewer
13. Submission of air quality impact assessment
14. Submission of air assessment of traffic noise and vibration
15. The hours of construction to be restricted to 08:00 to 18:00 hours on Monday to Friday, 08:00 to 13:00 hours on Saturday, with no work at any other time including Sundays and Public Holidays.
16. Details of the method, timing and duration of any pile driving operations connected with the construction of the development hereby approved to be approved
17. Development to proceed in accordance with the recommendations made in the submitted bats and water vole/otter reports to protect valued wildlife and the River Dane corridor.
18. A detailed method statement covering the implementation of said recommendations to be submitted to the Council for approval prior to commencement of works.