To consider the above application.
Minutes:
Consideration was given to the above application.
RESOLVED
That the application be approved subject to a prior appropriate Deed of Variation or new planning agreement under s106 TCPA which secures implementation of the management plan referred to in the Agreement of 19 September 1994 and of the woodland management plan and hydrological monitoring referred to in the planning agreement of 12 September 1994in respect of this site and subject to the following conditions:-
The replication where relevant of the existing 84 conditionsattached to the current permission for the quarry that deal with:
Hours of working
Traffic movements and protection of local highway network
Protection of public footpaths
Soil stripping
Methods of working
Tailings disposal
Plant, machinery and buildings
Noise
Dust
Surface water drainage, pollution control
Archaeology
Site maintenance
Restoration
Aftercare