Issue - meetings

10/3080W-Application to Extend the Time of Operations, Dingle Bank Quarry near Chelford - Application to Vary Conditions 3 and 4 Planning Consent 05/06/2558 to Increase the Period of Time by Six Years and 2 Months for Completion of Operations (Includ

Meeting: 15/06/2011 - Strategic Planning Board (Item 12)

12 10/3080W-Application to Extend the Time of Operations, Dingle Bank Quarry near Chelford - Application to Vary Conditions 3 and 4 Planning Consent 05/06/2558 to Increase the Period of Time by Six Years and 2 Months for Completion of Operations (Including Restoration) Dingle Bank Quarry, Holmes Chapel Road, Lower Withington for Mr D Walton, Sibelco UK Ltd pdf icon PDF 985 KB

To consider the above application.

Minutes:

Consideration was given to the above application.

 

RESOLVED

 

That the application be approved subject to a prior appropriate Deed of Variation or new planning agreement under s106 TCPA which secures implementation of the management plan referred to in the Agreement of 19 September 1994 and of the woodland management plan and hydrological monitoring referred to in the planning agreement of 12 September 1994in respect of this site and subject to the following conditions:-

 

  1. Mineral extraction to cease by 31st December 2016.
  2. Extraction areas to be restored by 31st December 2018 or within two years of cessation of extraction whichever is the earlier.

 

The replication where relevant of the existing 84 conditionsattached to the current permission for the quarry that deal with:

 

Hours of working

Traffic movements and protection of local highway network

Protection of public footpaths

Soil stripping

Methods of working

Tailings disposal

Plant, machinery and buildings

Noise

Dust

Surface water drainage, pollution control

Archaeology

Site maintenance

Restoration

Aftercare