10/3078W-Application to Extend the Time of Operations, Dingle Bank Quarry near Chelford - Application to Vary Conditions 7 and 8 of Planning Permission 5/05/0751 to Increase the Period of Time by just under Six Years for Completion of Operations (Inc

Meeting: 15/06/2011 - Strategic Planning Board (Item 11)

11 10/3078W-Application to Extend the Time of Operations, Dingle Bank Quarry near Chelford - Application to Vary Conditions 7 and 8 of Planning Permission 5/05/0751 to Increase the Period of Time by just under Six Years for Completion of Operations (Including Restoration), Dingle Bank Quarry, Holmes Chapel Road, Lower Withington for Mr D Walton, Sibelco UK Ltd pdf icon PDF 1 MB

To consider the above application.

Minutes:

Consideration was given to the above application.

 

RESOLVED

 

That the application be approved subject to a prior appropriate Deed of Variation or new planning agreement under s106 TCPA which secures implementation of nature conservation management plan referred to in the Agreement of 8 January 2007 relating to the site and subject to the following conditions:-

 

  1. Mineral extraction to cease by 31st December 2016.
  2. Extraction areas to be restored by 31st December 2018 or within two years of cessation of extraction whichever is the earlier.

 

The replication where relevant of the existing 57 conditionsattached to the current permission for the quarry that deal with:

 

Matters requiring approval

Hours of working

Traffic movements and protection of local highway network

Soil handling

Methods of working

Plant, machinery and buildings

Noise

Dust

Surface water drainage, pollution control

Lighting

Site maintenance

Ecology

Restoration

Aftercare