To consider the above report.
Additional documents:
Minutes:
Consideration was given to the above report.
(Councillor R Walker, the Ward Councillor and Mr Adams, the agent for the applicant attended the meeting and spoke in respect of the application).
RESOLVED
To issue permission in respect of outline planning application P06/1001 for the redevelopment of Stapeley Water Gardens subject to conditions as detailed in the decision by the Development Control Committee of the former Crewe and Nantwich Borough Council on 20th September 2007 and subject to the applicant completing and signing a Section 106 Agreement to secure:-
(1) the provision of 33% affordable housing on the site with:-
(a) a minimum provision of 26% for the development of Stapeley Manor site (Phase 1) on the basis that the level of provision for each phase will be identified in the first reserved matters application and that the overall provision will be 33% and
(b) one third 1-bed units, one third 2-bed units and one third 3-bed units across the whole site or the option for the provision of twelve 1-bed units, nineteen 2-bed units and nineteen 3-bed units and 50% social rented dwellings and 50% shared ownership/ Rent to Homebuy dwellings in all phases of residential development,
(2) phasing of the development and submission of a master plan to ensure that the site is brought forward as a mixed use development together with the provision and continuity of the relocated Water Gardens,
(3) commuted payments for off site highways works as per report P06/1001 (to include signage to direct traffic away from Nantwich town centre, contributions to the Willaston to Nantwich cycle link, contributions to works for the signalised junction at Wellington Road/ Park Road junction, contributions to traffic calming in London Road and Wellington Road, a sum for completion of a cycle link on South Crofts/ Monks Lane),
(4) the provision of an equipped play space to be provided in phase 1 of the residential development, and shared recreational open space and play space. A maintenance scheme for all areas of open space/ play equipment to be submitted.
(5) a maintenance scheme for ecological mitigation areas.