Decision details

25/4821/FUL - ENVIRONMENTAL SERVICES HUB, CLEDFORD LANE, MIDDLEWICH: Additional car parking, relocated bin store and a new security lodge

Decision Maker: Strategic Planning Board

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decisions:

Consideration was given to the above planning application.

 

The following attended the meeting and made representations in relation to the application:

 

Jonathan Pannell and Ralph Kemp (Agent / Applicant)

 

Members noted the content of the report.

 

RESOLVED:

 

That application 25/4821/FUL be APPROVED be as per the officer’s recommendation subject to the formal notification of an internal transfer of the financial contribution of £176,000 towards the Middlewich Eastern Bypass, and subject to the following conditions:

 

1)    Commencement of development (3 years)  

2)    Approved plans  

3)    Restriction on storage heights of materials or equipment to match that imposed on permission 15/2355W 

4)    Implementation of the travel plan approved under 15/2355W.

5)    Implementation of the submitted car park management strategy

6)    Restrictions on the hours of operation to reflect that contained on permission 15/2355W

7)    Implementation of the noise management plan approved under 15/2355W

8)    Adherence to maximum noise levels established under permission 15/2355W

9)    No burning of materials on site

10)Implementation of the mitigation identified in the air quality assessment

11)Submission of an updated conceptual model, phase II ground investigation and risk assessment, and where necessary a subsequent remediation strategy

12)Where deemed necessary under condition 12, submission of a verification report

13)Testing of all soils brought on site

14)Implementation of measures to deal with unexpected contamination

15)Implementation of the mitigation identified in the Ecological Assessment

16)Submission and implementation of a final updated construction environmental management plan and precautionary working method statements

17)Submission of a scheme to protect nesting birds

18)Submission of a scheme of biodiversity enhancement measures

19)Submission of a biodiversity net gain plan

20)Submission of detailed landscape planting scheme

21)Implementation of tree protection measures

22)Submission of final detailed drainage strategy with maximum discharge rate

23)Halite risk assessment

 

 

In the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions / informatives / planning obligations or reasons for approval/refusal) prior to the decision being issued, the Head of Planning has delegated authority to do so in consultation with the Chair of the Strategic Planning Board, provided that the changes do not exceed the substantive nature of the Committee’s

 

Councillors Moss and Jackson left the meeting at the end of this application.

 