Decision Maker: Strategic Planning Board
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Consideration was given to the above planning application.
The following attended the meeting and made representations in relation to the application:
Councillor Stewart Gardiner (Ward Councillor), Ian Anderson (Objector), John Finnan (Objector), Debbie Jamison (Objector) and Gary Halman (Agent / Applicant)
Members noted the content of the report and update report.
RESOLVED:
That application 25/1468/OUT be APPROVED as per the officer’s recommendation, subject to an S106 agreement and conditions:
|
S106 |
Amount |
Trigger |
|
Affordable Housing |
30% (65% Affordable Social Rent / 35% Intermediate)
|
In accordance with phasing plan to be submitted. |
|
Education |
£1,043,949.00 BASED ON 163 UNITS So the figure should be pro rata based on the approved RM number |
50% on first occupation and 50% by the time that 50% of the houses are occupied |
|
Health |
£903 at per dwelling or 1 bed unit in the case of C2 developments
|
50% on first occupation and 50% by the time that 50% of the houses are occupied |
|
Highways |
£320,000 be provided to fund a new Knutsford circular bus service for a two year period
|
At 50% occupancy |
|
Outdoor Sport |
£258,366.40 BASED ON 163 UNITS So the figure should be pro rata based on the approved RM number |
50% on first occupation and 50% by the time that 50% of the houses are occupied |
|
Indoor Sport |
£29,134 BASED ON 163 UNITS So the figure should be pro rata based on the approved RM number |
Prior to first occupation |
|
Public Open Space |
Private Management Company for Areas of Open Space
|
Prior to first occupation |
and the following conditions
1. Time limit for submission of reserved matters
2. Commencement within 2 years of approval of last reserved matter.
3. Submission of Reserved Matters
4. Compliance with plans and details
5. Trees – Tree retention
6. Any reserved matters application shall be supported by an Arboricultural Impact Assessment which shall include a Tree Protection (TPP) and Arboricultural Method Statement (AMS)
7. Trees – Levels to be agreed
8. Trees – Drainage to be agreed
9. Reserved matters application to be supported by a revised FRA and detailed drainage strategy / design, associated management / maintenance plan
10.Reserved matters application to be supported by scheme of foul and surface water
11.Drainage to be submitted, approved and implemented. Foul and surface water drainage shall be connected on separate systems.
12.Reserved matters application to include details of all hard and soft landscaping.
13.Reserved matters application to include details of maintenance and management of all landscaping
14.Reserved matters application to be supported by details of boundary treatments
15.Reserved matters to be supported by detailed proposed and finished ground and floor levels
16.Reserved matters to be supported by a noise impact assessment and mitigation
17.MAG – Height not to exceed 15m
18.MAG – Lighting to be caped at the horizontal with no upward light spill
19.MAG – During construction robust measures to prevent birds on site
20.MAG – Submission of a Bird Hazard Management Plan
21.MAG – No reflective materials
22.MAG - Measures to minimise and manage the creation of dust and smoke
23.Submission of a Phase II ground investigations survey and remediation strategy
24.Verification Report
25.Submission of soil verification report prior to first occupation of units to which they relate
26.Unexpected contamination
27.No trees, shrubs or hedges within the site which are shown as being retained on the approved plans shall be felled, uprooted, wilfully damaged or destroyed, cut back in any way or removed without the prior written consent of the Local Planning Authority.
28.Ecological enhancement
29.Biodiversity Net Gain
30.SuDs to avoid contamination of Booths Mere
31.Fencing off of part of Booths Mere to prevent recreational access/predation
32.Lighting to be approved
33.Enhancement of retained pond – Common Toad
34.Updated bat roost survey with any future reserved matters submission
35.Construction Environmental Management Plan submitted, approved and implemented
36.Ultra-low emission boilers
37.Nesting Birds
38.PROW improvements/management
39.Archaeology
40.Prior to occupation the pedestrian and cycle path as shown on Dwg No. 3565-PLA-XX-H2-DR-L-8020 be constructed.
41.Prior to occupation, the provision of two bus stops on Chelford Road to be delivered via a S278 Agreement.
42.Prior to submission of any reserved matters application submission of a full design code
43.Any reserved matters shall be accompanied by a code compliance statement
44.Limit the number of properties to a maximum of 145
In the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions / informatives / planning obligations or reasons for approval/refusal) prior to the decision being issued, the Head of Planning has delegated authority to do so in consultation with the Chairman of the Strategic Planning Board, provided that the changes do not exceed the substantive nature of the Committee’s decision.
Publication date: 09/06/2026
Date of decision: 27/05/2026
Decided at meeting: 27/05/2026 - Strategic Planning Board
Accompanying Documents: