Consideration was given to the work necessary to support the investigation of a new preferred route for the Poynton Relief Road which could then be incorporated as a protected line in the emerging Local Plan.
The report included details of the anticipated timescale required to prepare a submission for devolved Local Major Transport Scheme Funding. In addition the work proposed would better inform the continuing dialogue with Stockport Council on the interface of Poynton /Relief Road with the SEMMMS scheme at Chester Road.
RESOLVED
1. That Officers be authorised to commence the necessary work to support investigation of a new preferred route for the Poynton Relief Road when funding is identified and available; to include:
1.1 A draft Project Plan indicating the following key milestones,
timescales and decision points:
Milestone 1 – Approvals, Governance and Funding
Milestone 2 – Preliminary Investigation and Scoping
Milestone 3 – Data Gathering
Milestone 4 – Option Development and Appraisal
Milestone 5 – Consultation
Milestone 6 – Scheme Assessment Report and Preferred route.
2. That the indicative delivery programme and the key milestones for further Cabinet decisions, and the summary of the key decision points contained within Section 10, be noted.
Publication date: 19/09/2012
Date of decision: 17/09/2012
Decided at meeting: 17/09/2012 - Cabinet
Effective from: 27/09/2012