Issue details

CE 19/20-4 Poynton Relief Road - Final Approval to Underwrite Funding Gap, Appoint Contractor and Submit Final Business Case

To seek approval to confirm the formal underwriting of the funding gap for the Poynton Relief Road, submit the final business case to the Department for Transport, confirm the selection of the winning contractor and appoint the contractor to undertake limited advance works.

Decision type: Key

Reason Key: Expenditure > £1M;

Decision status: Recommendations Approved

Notice of proposed decision first published: 26/06/2019

Decision due: 10 Sep 2019 by Cabinet

Lead member: Deputy Leader of the Council

Lead director: Executive Director Place

Contact: Paul Griffiths Email: paul.griffiths@cheshireeast.gov.uk Tel: 01270 686353.

Private/Confidential Decision with Relevant Paragraph number: N/A