The Chairman read out the call-in
notice signed by 8 Members of the Council relating to the following
decision of the Transformation of Highways services sub-committee
held on 15 July
2010:
“RESOLVED
For the reasons set out in the report: -
1.
That approval be given to the strategic
direction of the procurement by way of the Managing Agent
Contractor model.
2.
That the structures that are, and have been, put in place to
support the procurement, and the significant resource implications,
be noted.
3.
That the advice concerning the appropriate procurement method,
namely by competitive dialogue, be noted.
4.
That the timetable shown in Appendix 1 of the report be
agreed.”
On behalf of the
Group of Members who had signed the call-in notice, Councillor C
Thorley addressed the Committee and outlined the reasons for the
call-in which were:
‘The
8 listed councillors below have called in the decision of the
Transforming Highways Sub Committee to Corporate Scrutiny on the
grounds:
-
That because of the value of this contract it should
be subject to scrutiny;
-
That Members have not been given the opportunity to
scrutinise other options for the delivery of Highway services, for
example, alliances with other authorities;
-
The impact on the employment of Highways Staff by
the proposed outsourcing.’
Councillor Thorley
added that:
- This was a matter of great concern
for the public of Cheshire East and for the staff currently
employed within Highways Services.
- There appeared to be an unnecessary
rush to complete the procurement process, which was likely prejudice
introducing arrangements to serve the whole of Cheshire.
- There were concerns about how any
new arrangements would serve the development control process.
Councillor T Beard, on behalf of the Call-in
group, referred to the fact that the existing the Highways Contract
with Bam Nuttall contained a clause to allow the Council to extend
the contract and that the Council should not at this stage, rule
out the possibility of invoking that clause.
Councillor R Menlove Environment Portfolio
Holder, outlined the basis of the
decision of the Transformation of Highways Sub-
Committee.
He explained that the Head of
Regeneration had outlined in her response to the Call-in (which was
appended to the agenda for this meeting) the reasons for the
original decision of the Transformation of Highways Sub- committee,
which were summarised as follows:
- The transformation of
the highways service is a key corporate priority and is one of the
five work streams of Total Transport. The decision to progress the
procurement of a new highways contract was taken by Cabinet in
April and a Sub-Committee was established with delegated powers to
make decisions relating to the project within the timelines
agreed.
- The procurement
process is using a Competitive Dialogue process which will allow
the Council to refine the scope of the new contract through the
procurement process over the coming weeks and months.
- In parallel to the
procurement process, the highways service is being re-shaped to
reflect the fact that big reductions in capital grant from
Government is expected from April 2011.
The re-shaping involves voluntary redundancy for some areas of the
service. Reductions in future capital
spend impacts directly on our revenue income and in simple terms
the Council cannot sustain the current structures.
- Member engagement
during the procurement process will be key to shaping the future service. The Cabinet Sub-Committee has delegated authority
to make decisions in relation to the new contract. An overview role from the scrutiny process
to inform the Sub-Committee will be essential to ensure the new
contract meets the needs of the Council from October 2011.
Councillor Menlove
explained that, as the existing contract was coming to an end, it
was prudent for the Council to consider as early as possible,
arrangements for Highways Services from 2011 and beyond.
In response to questions from members of the
committee, the Portfolio Holders for Environment and Procurement
Assets and Shared Services, supported by the Head Regeneration stated
that:
- It was common knowledge that the
Government intended to reduce not only funding for the current
financial year (in year savings) but also future budgets. The worst
case scenario suggested that this could be as much as 40%. The
likely impact of there being significant reductions in funds
available for Highways projects would in turn lead to the Council
having to review staffing levels. The
Council was facing these financial pressures, irrespective of the
outcome of the current procurement process.
- It was not possible to say at the
moment what the impact on staff would be in terms of TUPE
arrangements, however, the tendering process had a
robust assessment relating to how the new contract would address
TUPE and provide support to staff that transferred. TUPE protected
the terms and conditions of employees transferred, although it was
reported that there was no time limit specified in the regulations
as to the length of protection.
- There were currently
129 staff employed by Cheshire East affected by the Highways
contract and approximately 130 employed by the existing contractor
Bam Nuttall. The impact of any proposals on staff employed by Bam
Nuttall in relation to TUPE was not yet
clear, but much of the detail would be dealt with through the
competitive dialogue process.
- No staff could be
made compulsorily redundant at the point of transfer.
- The procurement of
Highways services was one element of the Council’s Total
Transport Programme, which itself was part of the Councils
Transformation programme, and although this particular element of
that process had not been listed in the Forward Plan, the
Transformation programme in total, had been.
- Cabinet had appointed
a sub- committee to carry out the detailed work in relation to the
procurement of Highways Services in April 2010 with delegated
authority to approve the procurement process. The only formal
meeting of the sub- committee had taken place on
15 July 2010. This meeting was
open to the public and all papers relating to it were published in
the usual manner and were in the public domain. The Sub- committee
consisted of 3 Cabinet members only, Councillors R Menlove, P Mason
and J Macrae, although at the meeting on 15 July, only Councillors
Mason and Macrae were present. A lot of preliminary work had been
undertaken by the sub- committee members supported by Councillor D
Stockton - Cabinet Support Member. This work had included visits to
other Local Authorities.
- Although Cabinet had
agreed that the Cabinet sub – committee would keep the
Environment and Prosperity Scrutiny committee appraised of the work
of the Sub- committee, this had not been communicated to the
sub-committee and it was conceded that consultation had not taken
place.
- Any failings of the
current contract could not be identified, however, the current
contract which began with the former Cheshire County Council in
2004, was subject to different performance measures and costs than
would be expected with any new contract, in that the Council was
looking to improve performance and reduce costs. The changing
landscape in connection with local authority funding also meant
that the Council would be looking at different delivery models,
which were likely to involve smaller capital programmes which in
turn would suggest a need for a reduced design function. The
Council was aware that the market for the provision of Highways
Services was currently buoyant and the Council should realistically
expect 5-10% efficiency savings in any new contract.
- The sub-committee had
visited Stockport Metropolitan Borough Council, Bedfordshire and
Gloucestershire County Councils and had also undertaken a site
visit to the Council’s current term contactor, Bann
Nuttall. The other local authorities
visited were
considered to be comparable authorities to Cheshire East. Each
Council operated a different model. Elsewhere in the country, there
were currently 7 or 8 Local Authorities that utilised the delivery
model favoured by the sub-committee and this was similar to long
standing arrangements operated by the Highways Agency.
- The Council had
commissioned expert legal advice on risk, particularly as the
Council was attempting to truncate the procurement process to
achieve the introduction of a new contract within 15 months. In
addition, the competitive dialogue process, which involved a
defined model, would mitigate any risks exposed by the truncated 15
month timescale.
- The costs of extending the existing contract with Bam Nuttall
was unknown at this stage, because this would depend on the
amount of work required by the Council.
- Staff were briefed
about the process on 16 June 2010
- There were a number
of key stages in the process starting with dialogue with potential
contactors in October/November 2010. The process to short list
would take place in January /February 2010This would be followed by
a process to analyse the bids. It was suggested that Overview and
Scrutiny Committees could play a role at each of these
stages.
- The detailed options
appraisals undertaken in relation to various contract models
commonly used by Local Government, as referred to in the report to
the Transformation of Highways Sub- committee, would be made
available to the Corporate Scrutiny Committee.
Note: Having answered questions, Councillors R
Menlove, PH Mason and D Stockton each declared a Personal and
Prejudicial interest in this matter and withdrew from the
meeting.
The Committee then considered the
report of the Borough Solicitor enclosing the grounds of the
call-in, the options available to the committee in respect of the
call-in, together the original report of the Transformation of
Highways services sub-committee held on 15 July
2010. The Committee also considered a formal response to the
call-in prepared by the Head of regeneration.
RESOLVED
–
(a)That in relation to Ground 1:
‘That because of the value of this Contract, it should be
subject to Scrutiny’
The
Transformation of Highways Sub-Committee be informed that the Committee offers no advice in
respect of this matter, on the grounds that the criteria used to
determine whether a matter should be subject to Overview and
Scrutiny does not specify a monetary value.
(b)That in relation to Ground 2:
‘That Members have not been
given the opportunity to scrutinise other options for the delivery
of highway services, for example alliances with other
authorities.’
The Portfolio Holders serving
on the Transformation of Highways Sub-Committee be requested to
open dialogue with immediate effect with this Committee and the
Environment and Prosperity Committee, with a view to consulting
fully with both committees in relation to their respective
interests in this matter, and the sub-committee be advised that the
two Overview and Scrutiny committees may wish to be given an
opportunity to scrutinise other options for the delivery of highway
services, including alliances with other authorities.
Additionally, Cabinet be
informed that this Committee believes there are lessons to be
learned from inadequacies identified in the consultation
arrangements in respect of the transformation of Highway Services
and would therefore urge Cabinet to put in place measures to ensure
that in future, Overview and Scrutiny committees are given an
opportunity to be consulted on all matters that appear within the
Forward plan in a timely fashion.
(c) That in respect of Ground
3:
‘The impact on the employment of highways staff by the
proposed outsourcing.’
The impact upon existing staff,
both Cheshire East Council and Bam Nuttall, be considered as a very important aspect of any
dialogue entered into and accordingly, should the transfer of
highways services proceed, this Council should apply TUPE
regulations in an exemplary manner.