Consideration was given to the above
application.
(Congleton Town Councillor Murphy and Mr M Ralph,
representing the applicant attended the meeting and spoke in
respect of the application).
RESOLVED
That the application be approved subject to -
(A) a
prior appropriate Legal Agreement under s106 Town & Country
Planning Act 1990 securing
(1)
Off-Site Highway Works:
to Mill Street, Stonehouse Green, Rood
Hill junction, Bridge Street/Duke Street, Victoria Street, and
Market Street, as described in the report
(2)
Market Provision:
including stalls, anchor points and sockets, as described in the
report. Prior to commencement of development a scheme shall be
agreed in writing with the LPA regarding the future operation of
the market within the development The scheme may append a
management agreement with CEBC as markets authority or may itself
set out arrangements necessary for the efficient operation of the
market, for example arrangements covering access to and use of
parking & loading areas & lifts, use of stores, offices and
other ancillary facilities, access times, stall erection &
dismantling, use of a power supply, maintenance & cleaning,
arrangements for the regulation of the market in its physical
environment.
(3)
The New Public Square:
including public access at all times, the installation of lighting
and power facilities, prior the
commencement of development, an approved scheme for precise layout,
materials specification, andan agreed scheme for design,
materials and landscaping, as described in the report. Prior to
commencement of development a further scheme shall be agreed in
writing with the LPA for the management, maintenance and continuing
use of the town square, its approaches and its facilities. The
scheme may append a management agreement or may itself set out
arrangements ensuring that the square functions as a focal point
for town events, for example arrangements may cover cleaning &
maintenance; use of lighting & electricity, lifts and other
facilities; use, operation & controls for public events;
management rights & responsibilities. Unless the Council agrees
otherwise in writing, no part of the development shall be occupied
until the town square and facilities have been made available for
public and market use in accordance with approved
schemes.
(4)
Active Frontage Use: including restrictions on
advertising space, shelving & display, and café use
overlooking the public square, as described in the
report
(5)
Travel Plans: and
monitoring costs as described in the report
(6)
Two Hours Free parking
(7)
Public Realm: a
contribution of £10,000 or 50% (whichever is the lower) to
the cost of a Public Realm Design Strategy commissioned by
Congleton Town Council. Any cost
savings which arise between (i) the
implementation of the specification contained in the Strategy or of
off-site highway works (if completed beforehand) and (ii) the
Applicant`s indicative costings for those works, shall be used to further
enhance the public realm.
and
(B) the following
conditions:-
General Conditions
- 3 Year
Time Limit.
- Development in accordance with the approved plans.
- All
external facing materials to be submitted and approved prior to the
commencement of development and implemented in accordance with the
approved details.
Design Related
Matters
- Development to be constructed with Green Roof, the details of
which shall be submitted and approved prior to the
commencement.
- Precise design and materials specification of the clock tower
submitted and approved prior to the commencement of
development.
- Minimum 100mm window reveal depths to the Mill Street
Façade unless otherwise agreed in writing by the Local
Planning Authority.
- Site
levels in accordance with approved drawings
Environmental
Health
- Environment Agency contaminated land condition.
- Further gas monitoring to be undertaken and scheme for gas
protection measures submitted and approved prior to commencement of
development.
- Scheme
for noise mitigation to achieve a BS8233: 1999 “Good
Standard “to hotel bedrooms to northern and western
facades to be submitted and approved prior to the commencement of
development.
- Scheme
for noise mitigation to plant and equipment within the development
for each phase of development in accordance with
BS4142.
- Submission of a Construction Environmental Management Plan to
cover the following areas: -
a) Restriction on hours of demolition, construction and deliveries
in accordance with those specified by Environmental Health
b) Submission of detailed scheme for measures to mitigate
dust
c) Details of road sweeper provision during demolition and
construction
d) Identification of storage and delivery areas within the
site
e) To prevent materials being burnt on site
- Scheme
for ventilation and extraction equipment for the café and
restaurant uses, extending to also include kitchen and bakery areas
within the proposed hotel and or food store, to be submitted and
approved for each phase of development and implemented
thereafter.
Retail Conditions
- Ensure
total net retail floorspace with the
food store is restricted to 3583m² with a maximum 2480m²
net convenience floorspace and a
maximum 1013m² net comparison
floorspace. In addition a percentage
based approach be adopted to allow
flexibility with a 70% convenience and 30% comparison goods
split.
- Restriction within the food store to prevent the inclusion of an
in-store pharmacy and post-office.
- Restriction on food store opening hours
Highway and Drainage
Conditions
- All
car parking spaces proposed within the development to be fully
available prior to the first use of the hereby-approved
development.
- Submission of surface water regulation and drainage strategy
prior to the commencement of development and implementation of
thereafter.
- Prior
to first occupation, precise details of cycle parking facilities to
be submitted and approved.
- Site
to be drained on a separate system with only foul drainage
connected into the existing foul public sewer which crosses the
site. Surface water to be discharged
into the Howty Brook.
Specific
Conditions
- Relocation of War plaque to a location to be agreed in writing
prior to the commencement of development and fully implemented
thereafter.
- No
development to commence until the temporary market facilities to
the Fairground Site have been fully implemented in accordance with
approved details unless otherwise agreed in writing with the Local
Planning Authority.
- Scheme
for detailed archaeological investigation to be submitted and
agreed prior to the commencement of development with a mechanism to
ensure a mitigation strategy is agreed with the Local Planning
Authority where necessary and fully implemented
thereafter.
- Prior
to commencement of development a scheme for CCTV to be submitted
and approved by the Local Planning Authority and fully implemented
thereafter.
- Prior
to commencement of development a scheme for external lighting for
the development site shall be submitted and approved by the Local
Planning Authority and fully implemented thereafter. This is to also include town direction
signage.
- Prior
to commencement of development detailed scheme for lighting and
physical security measures for the Princess Street underpass to be
submitted and approved by the Local Planning Authority and fully
implemented thereafter.
- Prior
to commencement of development detailed scheme for security
measures to all retail (excluding the food store) and internal
market units to be submitted and approved by the by the Local
Planning Authority to include details of internal roller shutters,
panic and intruder Alarms and CCTV and fully implemented
thereafter.
- Prior
to commencement of development, precise details of toilets which
are available for public use to be submitted and approved in
writing by the Local Planning Authority and fully implemented
thereafter.
- Detailed Landscape Plan to be submitted
- 5-year
landscape management condition
Ecology
- Detailed scheme for implementation of Bat habitat
creation/mitigation in accordance with recommendations within the
applicants report to be submitted and approved in writing by the
Local Planning Authority and fully implemented
thereafter
- Standard breeding bird
condition
A further four conditions were also
included:-
- Submission of a Site Waste Management Plan prior to the
commencement of development and fully implemented
thereafter
- Restriction to use classes - Restaurant & Café
Uses. Excluding café within food
store element which is included within the S106
Agreement
- Phasing mechanism to ensure:-
a)
That a construction timetable and overall build approach is agreed
with the Council prior to the commencement of development and is
fully implemented in accordance with those details unless otherwise
agreed in writing by the Local Planning Authority.
b)
Requiring that no part of the development be occupied until such
time as the development has been fully constructed (externally) andcompleted in accordance with the approved plans.
- Precise design of gable wall adjoining 19 Mill Street to be
submitted, agreed in writing and fully
implemented thereafter.
- Precise details of power voltage optimisation system to be submitted, agreed in writing and fully implemented
thereafter.
- Precise details of Shop Mobility and time frame for
implementation to be submitted and be agreed.
It was
requested that any amendments to the S106 agreement/Heads of Terms
should be brought back to the Board for their
consideration.