Agenda item

20/0604N Elephant & Castle Inn, 289, Newcastle Road, Shavington, CW2 5DZ- Variation of condition 2 & 24 of existing permission 17/2483N; Affordable Housing Development Comprising 45 no. dwellings & Ancillary Works

To consider the above application.

Minutes:

Consideration was given to the above application.

 

(Councillor Janet Clowes, the Adjacent Ward Councillor, and as requested by Main Road and Dig Lane Residents and Wynbunbury Parish Council; Parish Councillor Gordon McIntyre, from Shavington Parish Council; Simon Boone, speaking on behalf of the Shavington Traffic Regulation Order (TRO) Group; Bill Fulster, the representative for the Applicant; and Bill Bookers, SCP Highway Consultant for the applicant attended the virtual meeting and spoke in respect of the application).

 

RESOLVED-

 

That for the reasons set out in the report and in the verbal update to the Committee, the application be approved subject to the following conditions:

 

Approve subject to a Deed of Variation S106 / Unilateral Undertaking to link to the original

permission 17/2483N and the following conditions:

 

1)        Commencement of development (3 years from date or original permission )

2)        Development in accordance with approved plans on 17/2483N except as varied by this permission

3)        Materials as application 17/2483N

4)        Surfacing materials as approved 18/3014D

5)        100% affordable housing as 19/2671D

6)        Removal of permitted development rights for extensions classes A- E and means of enclosure/ boundary treatments forward of building line

7)        Nesting bird survey to be submitted

8)        Provision of features for breeding birds as approved under 18/3014D

9)        Compliance with Flood Risk Assessment (FRA) (ref: ES/16365/FRA Prepared by SCP) dated August 2016

10)     Implementation of landscaping

11)     LEAP (min 5 pieces of equipment) children’s play area /POS in accordance with details as approved under 18/3014D

12)     Contamination - Phase II investigation to be submitted prior to operational commencement

13)     Contamination - Importation of soil

14)     Remediation of unexpected contamination

15)     All Arboriculture works in accordance with Tree Care Consultancy Arboricultural Implication Assessment (Ref AIA1-CSE-SW) dated 11th May 2016

16)     Boundary treatments (inc 1.8m high close boarded to rear gardens adj in accordance with Noise Report recommendations) as approved under 18/3014D

17)     Levels, existing and proposed as approved under 18/3014D

18)     Noise mitigation scheme compliance with recommendations of report

19)     Details of construction and highways management plan, inc on site parking for contractors/storage during development as approved under 18/3014D

20)     Electric vehicle charging points to be provided for dwellings as approved under 18/3014D

21)     Residents Travel Information Pack

22)     Cycle storage details as approved under 18/3014D

23)     Bin Storage details as approved under 18/3014D

24)     No dwelling shall be occupied until the works to the highway along Main Road identified on Plans SCP/13269/SK30 Rev A and SCP/13289/ATR08 have been completed in accordance with the approved details

25)     Drainage strategy detailing on and off site drainage work to be submitted and implemented as approved

26)     Detailed calculations to support the chosen method of surface water drainage to be submitted and implemented as approved

27)     Compliance with bat as application 17/2483N

28)     Updated badger survey as approved under 18/3014D

29)     Submission and implementation of a scheme for the future management and maintenance of all communal open space be submitted and implemented as approved

30)     Bungalow/single storey accommodation - priority of occupation for over 55's/ persons reliant upon wheelchair

31)     Garden sheds provided as approved under 18/3014D

 

In order to give proper effect to the Board`s/Committee’s intentions and without changing the substance of the decision, authority is delegated to the Head of Development Management in consultation with the Chair (or in his absence the Vice Chair) of Southern Planning Committee, to correct any technical slip or omission in the wording of the resolution, between approval of the minutes and issue of the decision notice.

 

Should this application be the subject of an appeal, authority is approved to enter into a S106 Agreement to provide a Deed of Variation to link this proposal to the original permission under 17/2483N

Supporting documents: