To consider the above planning application.
Minutes:
Note: Councillor M Deakin left the meeting prior to consideration of this application.
Note: Prior to consideration of this application, the meeting was adjourned for refreshments.
Note: Alastair Skelton attended the meeting and addressed the Committee on behalf of the applicant.
The Committee considered a report regarding the above planning application and an oral report of the site inspection.
RESOLVED
(a) That, for the reasons set out in the report, the application be APPROVED subject to the completion of a S106 Agreement to secure:
S106 |
Amount |
Triggers |
Affordable Housing
|
30% - 65% Affordable Rent / 35% Intermediate
Submission of Affordable Housing Statement |
If any market housing, 50% open market occupied prior to affordable provision.
Prior to issuing of decision notice |
Education
|
Primary: £21,693 Total: £21,693 |
Prior to 50% occupation |
Public Open Space
|
On-site provision as shown on plan. Submission of a Private Management Plan in perpetuity |
Prior to occupation |
and the following conditions:
1. Time Limit (Outline)
2. Submission of reserved matters (landscaping to include native hedgerows to eastern boundary)
3. Reserved Matters application made within 3 years
4. Development in accordance with approved plans
5. Prior submission/approval of levels
6. Reserved Matters scheme should be supported by an updated AIA/Tree Protection Scheme in accordance with BS 5837
7. Retention of existing hedgerow (Ecology)
8. Nesting birds
9. Prior submission of an ecological enhancement strategy
10. Prior submission/approval of the LPA for external lighting
11. Prior submission/approval of a piling method statement
12. Prior submission/approval of an Environmental Management Plan (EMP)
13. Prior submission/approval of a residents travel information pack
14. Provision of electric vehicle charging infrastructure
15. Prior submission/approval that any gas boiler installations proposed are to a certain emission standard
16. Prior submission/approval of a phase 1 contaminated land report
17. Submission/approval of a verification report
18. Submission/approval of a soil verification report
19. works to stop if contamination is identified
20. Prior submission of a surface water drainage scheme and associated management and maintenance plan
21. Implementation of Flood Risk Assessment
22. Prior submission/approval of a PROW Scheme of Management
23. Line of PROW shall be marked out on development site prior to commencement of development
24. Prior submission/approval of a Construction Management Plan
(b) That, in order to give proper effect to the Committee’s intentions and without changing the substance of the decision, authority be delegated to the Head of Planning (Regulation), in consultation with the Chairman (or in his absence the Vice Chairman) of Southern Planning Committee, to correct any technical slip or omission in the wording of the resolution, before issue of the decision notice.
(c) That, should this application be subject to an appeal, approval be given to enter into a S106 Agreement with the following Heads of Terms:
S106 |
Amount |
Triggers |
Affordable Housing
|
30% - 65% Affordable Rent / 35% Intermediate
Submission of Affordable Housing Statement |
If any market housing, 50% open market occupied prior to affordable provision.
Prior to issuing of decision notice |
Education
|
Primary: £21,693 Total: £21,693 |
Prior to 50% occupation |
Public Open Space
|
On-site provision as shown on plan. Submission of a Private Management Plan in perpetuity |
Prior to occupation |
Supporting documents: