09/1480N-Erection of a Building for use within Class B8, use Class B2 with ancillary offices, security gatehouse and associated car parking and landscaping, Basford West Development Site, Crewe Road, Shavington-cum-Gresty, Crewe for Goodman

Meeting: 20/01/2010 - Strategic Planning Board (Item 163)

163 09/1480N-Erection of a Building for use within Class B8, use Class B2 with ancillary offices, security gatehouse and associated car parking and landscaping, Basford West Development Site, Crewe Road, Shavington-cum-Gresty, Crewe for Goodman pdf icon PDF 238 KB

To consider the above application.

Minutes:

Consideration was given to the above application.

 

(Mr Wild, a representative of Basford East Basford West Action Group and Mr Rolinson, the agent for the applicant attended the meeting and spoke in respect of the application).

 

RESOLVED

 

     That the application be approved subject to the completion and signing of a deed of variation to implement the Habitat Management Plan for the planting on both sides of the spine road including the planting around the water storage ponds and to provide an appendix to secure a management and maintenance regime for the public art, street furniture including seating, fencing, access gates, barriers or other means of control, litter picking, control of dog waste, litter bins, dog waste  bins, hard surfaces including paths and any related waymarking and maintenance of ponds and culverts, subject to Schedule 5 Part III of the S106 Agreement be varied in respect of the provision of the pedestrian cycle link at the rear of the Cheshire Cheese and subject to the following conditions:-

 

1. Plans

2. Samples of materials to be submitted for approval.

3. Landscaping to be implemented in accordance with the submitted amended plans (as amended following negotiations)

4. Spine Road and its western arm to be completed and available for use before the unit is first occupied.

5. Wildlife tunnels to be provided in spine road.

6. Access to Unit A to be provided before the unit is first occupied.

7. Car parking to be provided before the unit is first occupied.

8. Cycle parking and motor cycle parking to be provided before the unit is first occupied.

9. Details of showers, changing facilities and lockers for use by persons cycling to work to be submitted approved and provided and to be made available to all staff working at the unit.

10. Details of driver overnight facilities to be submitted approved and implemented.

11. Development to comply with Noise Assessment.

12. Details of measures to reduce noise from mechanical service plant to be submitted approved and implemented.

13. Submission of Construction Management Plan for Phase1& 2 combined.

1.        Flood risk attenuation measures from this site to Gresty Brook to be provided before unit A is first occupied.

2.        Full details of security fencing

3.        Details of waste recycling and storage facilities.

4.          Details of lighting scheme to be submitted, approved and implemented.

5.          Details of measures to improve the energy efficiency of the design of the building to be submitted approved and implemented.

6.          Details of energy efficiency measures to be used by the operator in the use of the premises to be submitted, approved and implemented.

7.          Hours of working 08:00-17:30 Monday to Friday, any variation to be agreed in writing-(Officers to inform Ward Councillors and Parish Councillors of any variation to the hours operation during construction)

In addition it was agreed that (A) authority be delegated to the Head of Planning and Policy in consultation with the Chairman and Vice Chairman to secure an increase in the percentage mix of evergreen  ...  view the full minutes text for item 163