09/3066C - Proposed B1 Office Building, Henry Alty, Knutsford Road, Cranage, Holmes Chapel for Cheshire Prop (Cranage) 1LTD & 2LTD

Meeting: 02/12/2009 - Strategic Planning Board (Item 138)

138 09/3066C - Proposed B1 Office Building, Henry Alty, Knutsford Road, Cranage, Holmes Chapel for Cheshire Prop (Cranage) 1LTD & 2LTD pdf icon PDF 419 KB

To consider the above application. 

Minutes:

(During consideration of the application Councillor D Brown arrived to the meeting).

 

Consideration was given to the above application.

 

(The Ward Councillor L Gilbert, Parish Councillor John Halstead representing Cranage Parish Council, Mr Perkin, an objector and Mr Thomas, representing the applicant attended the meeting and spoke in respect of the application).

 

RESOLVED

 

That the application be approved subject to the following conditions:-

 

1. Commence within 3 years

2. Development in accordance with submitted plans

      3. Use of the development to be restricted to Use Class B1 only

      4. Details of materials to be submitted

      5. Landscaping scheme to be submitted

      6. Landscaping scheme to be implemented

7.Site management plan to be submitted including details of construction of underground car park

      8. Wheel washing facilities to be provided

      9. Lighting plan to be submitted and implemented

      10. Review of implemented lighting after 3 months

11. Detailed Travel Plan to be submitted and implemented

12. Details of the parapet wall surrounding the entrance to the underground car park to be submitted prior to development

13. Time limit on the hours of construction (M-F 9.00 to 18.00 & Saturday 9.00 to 13.00; 14. No working Sunday or Bank Holiday)

15. Limits on use of piling foundations (M-F 10.00 to 16.00; No working Saturday, Sunday or Bank Holiday)

16. Submission of a revised tree protection plan and arboricultural method statement

17. Submission, approval and implementation of a revised schedule of all proposed tree works.

18. Submission of details, approval and implementation of special construction for areas of hard surfacing within tree root protection zones

 

19. Drainage scheme including sustainable drainage and water attenuation (SUDS) to be provided and implemented

 

20. Prior to the commencement of development details of the main construction elements shall be submitted to an approved in writing of the materials to be used in the construction of the building hereby approved to meet the requirements of Jodrell Bank Telescope

 

In addition the following conditions were also included:-

 

  1. Additional conditions recommended by the Highways Officer concerning:-

 

i.        Submission and approval of a Forward Plan

ii.      Detailed design drawings for reconfiguration of the northern access

iii.    Visibility splays to be provided in accordance with plan SK003 Rev P2

iv.    Provision of cycle tracks and shower and changing facilities