To consider the above planning application.
Minutes:
Note: The Southern Area Manager reported that in respect of protected species there was no satisfactory alternative to the proposal.
Note: Mrs R Pickles (supporter) attended the meeting and addressed the Committee on this matter.
The Committee considered a report regarding the above planning application.
RESOLVED – That the application be APPROVED subject to the following conditions:
1. Submission of reserved matters
2. Implementation of reserved matters
3. Time limit for submission of reserved matters
4. Development in accordance with submitted plans
5. Samples of materials to be submitted
6. Construction specification / method statement, including hours of construction, access, demolition, disposal of spoil, wheel wash
7. Noise assessment required
8. Air quality assessment
9. A scheme for the acoustic enclosure of fans and other machinery required
10. Odour extraction system required
11. Dust mitigation during construction
12. External lighting to be agreed prior to development
13. Protection from noise during construction (hours of construction)
14. Time constraints on any pile driving
15. Contaminated land desk-top assessment to be submitted
16. Details of drainage
17. Sustainable urban drainage -scheme to be submitted
18. A scheme for the provision and management of a buffer zone alongside the brook
19. A scheme to ensure finished floor levels of the proposed building are set no lower than 92.91m above Ordnance Datum (mAOD) to be submitted.
20. Tree protection
21. Tree pruning / felling specification
22. Protection of breeding birds
23. Details of landscaping to be submitted
24. Implementation of landscaping
25. Landscape and habitat management plan
26. Bat mitigation/enhancement
27. Woodland management plan
28. All parking, access and traffic areas to be completed and marked out prior to first occupation.
29. Cycle storage facilities for care home
30. Implementation of a programme of archaeological work in accordance with a written scheme of investigation
31. Provision of features into the landscaping scheme suitable for use by breeding birds including swifts.
32. Prior to the commencement of any works between 1st March and 31st August in any year, a detailed survey is required to check for nesting birds.
33. Travel Plan to be submitted and agreed.