Issue - meetings

7/2009/CCC/4 - New Post 16 Centre incorporating 3 Storey L-shaped Building with External Social Space and General Improvements to the Site including Parking and Floodlighting to Tennis Courts, Brine Leas High School, Audlem Road, Nantwich

Meeting: 27/05/2009 - Strategic Planning Board (Item 43)

43 7/2009/CCC/4 - New Post 16 Centre incorporating 3 Storey L-shaped Building with External Social Space and General Improvements to the Site including Parking and Floodlighting to Tennis Courts, Brine Leas High School, Audlem Road, Nantwich pdf icon PDF 478 KB

To consider the planning application 7/2009/CCC/4

Minutes:

Note: Councillor Arthur Moran (Ward Councillor) and Mr Andrew Cliffe, (Headteacher at Brine Leas High School) attended the meeting and spoke in respect of the application.

 

The Board considered a report on the above application.

 

Great Crested Newts were European Protected Species and no work could commence on the site until a Licence under the Habitat Directive had been granted granted by Natural England.

 

The recommendation for approval had been made mindful of the tests required for a licence to be granted including whether the development was considered to be of sufficient importance in the public interest.  The nature of the development and the proposed mitigation were considered to be sufficient to satisfy the relevant tests in the Habitat Regulations,

 

RESOLVED:

 

That the application be APPROVEDsubject to the following conditions:

 

1. Standard Time

2. In accordance with approved drawings

3. Samples /detail of materials on external elevations

4. Revised Landscaping Scheme and aftercare plan

5. Implementation and maintenance of landscaping

6. Highways Construction Management Plan

7. Provision of floodlighting and view after one month

8. Hours of use of floodlighting

9. Update, submission and implementation of school travel plan

10. To comply with Amphibian Mitigation Strategy

11. Require further details of tree protection measures

12. Provision of bird / bat boxes

13. Provision of car parking – surfaced and marked out

14. Details of secure and covered cycle parking

15. Details of motorcycle parking

16. Provision of tennis court / MUGA facility before development is first occupied

17. Drainage works to be implemented

18. Off-site highways improvements to be implemented through the school travel plan

19. Details of rebound fencing to tennis court / MUGA facility

20. Details of fencing to eastern boundary

21. Scheme for improvement of playing field drainage

22. Wheel Washing

23. Hours of Construction

24. Details of piling

25. Continuity of parking provision on site

26. Provision of Waste Management Facility