To consider the above planning application.
Minutes:
The Committee considered a report regarding the above planning application.
RESOLVED – That authority be DELEGATED to the Development Management and Building Control Manager in consultation with the Chairman to approve the application for the reasons set out in the report, subject to:
(a) the satisfactory completion of a Unilateral Undertaking/Planning Obligation to secure pedestrian crossing(s), following further discussions between the Development Management and Building Control Manager and the Highways Manager.
(b) the following conditions:
1) 5 year temporary consent and area restored thereafter
2) Development to be carried out in accordance with approved plans
3) Materials / colours to be submitted
4) Hours of construction limited
5) Hours of piling limited
6) Acoustic Enclosure of any Fans / Compressors to be submitted
Note: Following consideration of this application, the meeting was adjourned for ten minutes for a break.