12/3869W-Variation of conditions 5 (b), 5 (c) (relating to hours of working) and 6 (relating to traffic movements) of approval 5/06/1782P for the erection of plant, machinery and utilisation of the former garage and lorry parking facilities for baggi

Meeting: 13/03/2013 - Strategic Planning Board (Item 162)

162 12/3869W-Variation of conditions 5 (b), 5 (c) (relating to hours of working) and 6 (relating to traffic movements) of approval 5/06/1782P for the erection of plant, machinery and utilisation of the former garage and lorry parking facilities for bagging and storing dried ready mixed concrete, mortar and turf dressing products, Eaton Hall Quarry, Manchester Road, Congleton for Tarmac Building Products Ltd pdf icon PDF 466 KB

To consider the above application.

Minutes:

Consideration was given to the above application.

 

RESOLVED

 

That for the reasons set out in the report and in the update to Board, the application be approved subject to entering into a Unilateral Undertaking in which 7 days written notice is given of the implementation of this varied consent, confirming from the date that they will be undertaking operations under the new permission and its conditions, and will not revert to/undertake operations under the existing permission 5/06/1782P and subject to the following conditions:-

 

1) The development hereby approved shall begin no later than three years beginning with the date of this permission.

 

 

2) The development hereby approved shall be carried out in accordance with the following documents, except where these may be modified by the conditions below;

 

Planning Application form dated 8 October 2012

Supporting Statement/Letter from applicant dated 8 October 2012

Amec Noise Assessment dated 8 October 2012

Location Plan 8 October 2012

Site Plan dated 18 October 2012

 

3) At least seven days prior written notice of the commencement of development shall be given to the Local Planning Authority

 

4) From the commencement of development to its completion, a copy of the permission, including all documents hereby approved and any other documents subsequently approved, in accordance with the permission, shall always be available at the site office for inspection during normal working hours

 

5) The operation of the development hereby approved shall be restricted to the following periods;

 

a)    for vehicle movements unloading and loading – at all times between 04.00 Monday to 18.00 Saturday. 

b)    For sand processing and drying – 06.00 to 18.00 Monday to Saturday (all year)

c)    For maintenance 07.00 to 19.00 Monday to Saturday (all year)

 

6) The permitted vehicles movements related to this development shall not exceed a maximum of 42 (21 in, 21 out) Heavy Goods Vehicles movements on any working day is averaged out over the calendar month.  Of these, a permitted daily maximum of 14 (7 in, 7 out) Heavy Goods Vehicles carrying imported materials.

 

7) A record shall be kept by the operator of the number of Heavy Good Vehicles which enter and leave the site on any working day, week and calendar month, and of their loads, and a copy of these vehicle numbers and load details shall be submitted to the Mineral Planning Authority at three monthly intervals during the operational life of the site. 

 

8) The close board fence approved under application 5/06/1782p (submitted on drawings 15811-S03b & 15811-S04) shall be retained throughout the duration of the operations. 

 

9) The approved noise monitoring scheme under application 5/06/1782p for the monitoring of the approved bagging facility shall remain implemented.

 

10) The best practicable means shall be used to minimise noise levels from all plant, machinery and vehicles.  All plant machinery and vehicles shall be maintained in efficient order in accordance with the manufacturers instructions

 

11) The dust control measures approved under application 5/06/1782p shall be retained.

 

12) Following the completion of development the site shall be restored  ...  view the full minutes text for item 162