09/3498C Demolition of four dwellings, a coach and HGV depot building, a workshop and various outbuildings and construction of twenty dwellings with associated garages and car parking and alterations to access road (resubmission of 08/1019/FUL), Land

Meeting: 11/08/2010 - Southern Planning Committee (Item 51)

51 09/3498C Demolition of four dwellings, a coach and HGV depot building, a workshop and various outbuildings and construction of twenty dwellings with associated garages and car parking and alterations to access road (resubmission of 08/1019/FUL), Land at Forge Lane, Congleton for Mirwell Homes Ltd c/o Emery Planning Partnership pdf icon PDF 624 KB

To consider the above planning application.

Minutes:

Note: Mrs C Featherstone (objector) and Mr R Gascoigne, Emery Planning, (on behalf of the applicant) attended the meeting and addressed the Committee on this matter.

 

Note: Ms A Brightmore, Mr T Radage and Mr M Robinson (objectors) had registered their intention to address the Committee on this matter but did not speak.

 

The Committee considered a report regarding the above planning application and an oral update by the Principal Planning Officer.

 

RESOLVED – That the application be APPROVED subject to

 

(a) the prior completion of a S106 Agreement to secure:

 

(i) a detailed woodland management plan

(ii) a contribution for local traffic management issues

(iii) a substantial start on site (comprising completion of roads, drainage and 25% of the housing) within 12 months, failing which, an overage clause as per (iv)

(iv) updated financial appraisal in accordance with a methodology to be agreed with the District Valuer to secure appropriate financial contributions in lieu of affordable housing if the economics of provision allow

 

(b) the following conditions:

 

1.                  3-year Time Limit

2.                  Development in accordance with approved plans

3.                  Materials to be agreed prior to construction commencing (including window frames, doors and balconies)

4.                  Standard contaminated land condition

5.                  Scheme for noise mitigation within new dwellings

6.                  Restriction on construction hours to 08.00 to 18.00 Monday to Friday, 08.00 to 13.00 Saturday and no work on Sundays or Bank Holidays

7.                  Removal of permitted development rights

8.                  Submission of a scheme of landscaping to include replacement hedge planting using native species

9.                  Implementation and 5 years landscape maintenance condition

10.             Tree protection measures

11.             Precise details of boundary treatments

12.             Precise layout of car parking court to be submitted and agreed prior to commencement of development

13.             Precise details of retaining wall to the western site boundary to be submitted and agreed

14.             Scheme for ecological enhancements for bats and birds

15.             Site levels condition

16.             Submission of a detailed suite of plans relating to the off site highway works

17.             Compliance with the recommendations contained within the ecological report

18.              Provision of a sustainable urban drainage system (SUDS)