10/1657N New Building on Land to the Rear of Existing Public House Incorporating 15 Bedroom Guest Accommodation and Conference Facility. The Enclosing on Existing Deck Area, Holly Bush Inn, Crewe Road, Winterley, Sandbach, CW11 4RF for Mr & Mrs R Wil

Meeting: 30/06/2010 - Southern Planning Committee (Item 25)

25 10/1657N New Building on Land to the Rear of Existing Public House Incorporating 15 Bedroom Guest Accommodation and Conference Facility. The Enclosing of Existing Deck Area, Holly Bush Inn, Crewe Road, Winterley, Sandbach, CW11 4RF for Mr & Mrs R Williams pdf icon PDF 566 KB

To consider the above planning application.

Minutes:

The Committee gave consideration to a report on Planning Application No. 10/1657N (Holly Bush Inn, Winterley) together with an update.

 

Notes: (1) Councillor J Hammond, the Ward Councillor who had called-in this application, was in attendance and addressed the Committee on this matter. Having declared a personal and prejudicial interest in this item, Councillor J Hammond withdrew from the meeting following his statement;

 

(2) Mr R Hovey, member of Haslington Parish Council (objector), Mr L Playle (objector) were in attendance and addressed the Committee on this matter; and

 

(3) Mr R Moran (agent for the applicant) was in attendance and addressed the Committee on this matter.  It was noted that Mr Moran had exceeded the deadline to register his intention to speak.  The Committee agreed that in the interests of balance, he be allowed to speak in accordance with Paragraph 2.8 of the Protocol for Public Speaking Rights.)

 

RESOLVED:

 

That Application No. 10/1657N be APPROVED subject to the following conditions -

 

1.         Commence development within 3 years

2.         Development in accordance with approved plans

3.         Materials to be submitted and approved

4.         Details of hard and soft surfacing materials to be submitted and approved

5.         Scheme of landscaping to be submitted and approved

6.         Scheme of landscaping to be implemented

7.         Scheme of drainage to be submitted and approved

8.         Notwithstanding submitted information, details of boundary treatment to be submitted

9.         Parking to be provided prior to first occupation of the guest       accommodation

10.       Noise attenuation measures to be implemented prior to development being first brought into use

11.       Scheme for the acoustic enclosure of any fans, compressors or other equipment with the potential to create noise, to be submitted to, and approved prior to the commencement of development

12.       Hours of construction to 08.00 – 18.00 Monday to Friday; 08.00 – 13.00 on Saturdays and not at all on Sundays or Bank Holiday Mondays

13.       Details of pile driving to be submitted

14.       Details of any floodlighting or security lighting to be submitted and approved.

15.       Details of cycle storage to be submitted and approved.

16.       Submission approval and implementation of slab levels