10/0692W-To carry out Development without Complying with Conditions Attached to 7/P05/1326 to Extend the Operation Life of the Maw Green Landfill Facility to 31 December 2017, Restoration by 31 December 2018, permit a Variation to the Sequence of Pha

Meeting: 02/06/2010 - Strategic Planning Board (Item 9)

9 10/0692W-To carry out Development without Complying with Conditions Attached to 7/P05/1326 to Extend the Operation Life of the Maw Green Landfill Facility to 31 December 2017, Restoration by 31 December 2018, permit a Variation to the Sequence of Phasing of Operations along with Minor re-contouring to the South East of the Site, Maw Green Landfill Site, Maw Green Road, Crewe for 3C Waste Ltd pdf icon PDF 296 KB

To consider the above application.

Minutes:

Consideration was given to the above application.

 

RESOLVED

 

That the application be approved subject to a deed of variation to the existing Section 106 PlanningObligation to secure:

 

-          diversion and maintenance in perpetuity Fowle Brook;

-          long-term management of the restored nature conservation area on Cell 9a for a period of 15 years following the restoration of Cell 9a

-          monitoring and maintenance of the leachate control system;

-          monitoring the generation and extraction of landfill gas;

-          Heavy Goods Vehicle routing; and

-          Maintenance and management of a length of Maw Green Road.

 

Subject to the all the conditions attached to permission 7/P05/1326 unless amended by those below and;

 

1. Approved plans

2. Revisions to existing approved restoration plan – replace with in interim and final restoration plan and associated restoration conditions

3. Revisions to existing phasing plans and associated phasing conditions

4. Revisions to existing pre-settlement contours, and associated contouring conditions

5. Additional surface water lagoon plan

6. Extension of time to 31st December 2017 with interim restoration of the site within 12 months or no later than 31st December 2018

7. Final restoration as final restoration plan to be no later than 12 months following the cessation of production of leachate and landfill gas

8. Interim and final restoration proposals to be amended to include rough tussocky grassland to provide suitable habitat for ground nesting birds

9. Liaison Committee Scheme

10. Noise limits

11. Noise Monitoring Scheme

12. Best practical site management for noise/ dust/ odour/ flies/ vermin/ birds/ litter control as per ES

13. Securing the RAMS outlined in both the ES and the updated Ecological Report to be implemented throughout the life of the development in accordance with the approved ES and Ecological Report; and

14. Amend the interim and final restoration proposal to also include the provision of two additional ponds to mitigate for those lost to the re-capping in cell 10b.

 

The following informatives should be attached to any decision notice.

 

Natural England

 

The developer should be made aware that should a protected species be subsequently found on the site, all work should stop until further surveys for the species are carried out and a suitable mitigation package for the species is developed.

 

Environment Agency

 

Fowle Brook is designated "main river". In accordance with the Water Resources Act 1991 and the Land Drainage Byelaws, the Environment Agency's prior written consent is required for any proposed works or structures in, under, over, or within 8 metres of the top of the banks of Fowle Brook.

 

This site already has a permit. The changes are minor in nature and would not require a variation to the permit.

 

Network Rail

 

The materials contained within the site subject to the applicants control should be stored and processed in a way which prevents over spilling onto Network Rail land and should not pose excessive risk to fire. If hazardous materials are likely to be sited on the land then Network Rail must  ...  view the full minutes text for item 9