Decision Maker: Portfolio Holder for Communities
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Conditional upon an amendment being made through planning to the internal layout of the facility, the Portfolio Holder for Communities is being asked to:
1 approve the issue of the Notice to Proceed and entry into the construction contract with Rock Merchanting Limited (T/A Pulse Design & Build); and
2 approve the temporary complete closure of the Leisure Centre in order to accelerate the construction.
That, conditional upon an amendment being made through planning to the internal layout of the facility, the Portfolio Holder
1 approves the issue of the Notice to Proceed and entry into the construction contract with Rock Merchanting Limited (T/A Pulse Design & Build); and
2 approves the temporary complete closure of the Leisure Centre in order to accelerate the construction programme.
Publication date: 22/12/2020
Date of decision: 22/12/2020
Effective from: 07/01/2021