6 Medium Term Financial Strategy Assumptions and Reporting Cycle for 2024/25 to 2028/29 PDF 333 KB
To consider the report on the baseline assumptions for net revenue expenditure and core funding, to assist with development of the Medium-Term Financial Strategy 2025 to 2029.
Additional documents:
Minutes:
The Sub-Committee considered a report which set out the baseline assumptions for net revenue expenditure and core funding, to assist with development of the Medium-Term Financial Strategy 2025 to 2029.
The Sub-Committee was being asked to approve the assumptions and to form a Working Group to review them further over the summer with the aim of feeding back in September.
The Sub-Committee was also being asked to approve the financial reporting timetable at Appendix C to the report.
In response to members’ questions and comments, officers advised as follows:
The Sub Committee highlighted that the baseline assumptions were the initial interim assumptions for the start of the process, and these would be considered by the Working Group and any changes to them would be reported back to the Sub Committee.
It was requested that the Working Group meet via Teams and that an invite be sent out for the initial meeting to all members of the Sub Committee.
RESOLVED (by majority): That the Sub Committee
1 approve the budget assumptions underpinning the Medium-Term Financial Strategy for 2025-29, for planning purposes, as set out in Appendix A1 to the report.
2 approve the setting up of a Finance Sub Committee Assumptions Working Group to meet informally with the Chief Finance Officer to review the current assumptions with the aim of feeding back to the September committee meeting; the Group to be made up of at least four members of the Sub Committee.
3 approve indicative savings targets and budget envelopes for each committee for 2025/26, as shown in Table 7 of the report and Appendix B to the report.
4 approve the combined Budget setting and transformation timeline, as set out in Appendix C to the report.
5 note the 2024/25 Budget change items progress, as set out in Appendix D to the report.